Project progress
DOMIBUS:.
- Due to 2 bugs detected (internally) in Domibus version 4.1 FR, it was decided to anticipate the release 4.1.1, adjusting the previously defined the scope and anticipating the release date since the bugs detected required immediate correction. The previously defined scope for 4.1.1 was pushed to version 4.1.2. Consequently the release date for 4.1.2 was adjusted to reflect the, above mentioned, changes in the release planning.
- An assessment exercise and revison was conducted on the existing testing processes, in order to allow the detection of these sort of issues in earlier stages of the release process.
SMP:
- Bugfix release 4.1.1 on schedule (SMP authentication improvement with CRL and CA | Improve handling shared keystore in Cluster environment | Bug fixing)
SML:
- Attempt to activate DNSSEC failed in production because the DNS server was not powerful enough to support DNSSEC. This resulted in a downtime of the SML from 18h00 on 28/08/2019 to 02h00 on 29/08/2019. The datacentre improved the performances of the DNS server and asked us to try again, but first we prefer to execute load testing on the DNS server before trying another attempt. We asked the datacentre to provide us with a production-like test environment.
- SML 4.0.1 bug fix was released in acceptance on the as planned. However due to Data Center delays in setting up the Production environment according to the new security standards to be adopted (https implementation) it was decided to postpone the production release to
eTrustEx adapter replacement Access Point plugin:
- Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) progressing. FR Release date set for . Despite the fact that most of the development work being close to completion, the changes introduced in this version will require extensive and detailed testing. Moreover long periods of unavailability of team members are foreseen due to parental leave.
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 16% | ONGOING | Release date and scope redefined follow the anticipation of the 4.1.1 release |
12/Nov/19 | 21/Sep/20 | - | NOT STARTED | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SML 4.0.1 | 18/Jun/19 | 2/Oct/19 | 96% | DELAYED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 78% | ONGOING | Bug fix release |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 65% | ONGOING | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 31/Mar/20 | - | NOT STARTED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |