Date: 

 

Attendees


Project progress

DOMIBUS:.

  • Activities for release 4.1.2, planned for , following the scope adjustment required due to the anticipation of the release of 4.1.1 are progressing at the expected pace. Concurrently the work on version 4.2 has also been initiated.

SMP:

  • Bugfix release 4.1.1  (SMP authentication improvement with CRL and CA | Improve handling shared keystore in Cluster environment | Bug fixing) was successfully released on the 

SML:

  • SML 4.0.1 bug fix was released in acceptance on the   as planned. And following the extra time required by the Data Center to set up the Production environment according to the new security standards to be adopted (https implementation) this version was released in production on the  

eTrustEx adapter replacement Access Point plugin:

  • Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) ongoing  (FR  ).  Focus on assisting the entities using the adapter with the migration process to the eDelivery Acc Point - eTrustEx Plugin, seven onboarding process are ongoing at this stage, and on providing training to the SO.
    • Meeting with the Portuguese Assembleia da Republic took place on the  
    • Meeting with OP in Luxembourg to discuss the best approach to the migration of their adapter instance on the  

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milestones progress:


Milestone Title

Start Date

End Date

% complete

Status 

Comments

Domibus 4.0.210/Dec/1811/Feb/19100%


COMPLETED



Domibus 4.1 RC24/Sep/1820/May/19100%

COMPLETED

Release date postponed from the 1st March to 20th May
Domibus 4.1 FR21/Mar/1931/Jul/19100%

COMPLETED

Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July
Domibus 4.1.101/Aug/1916/Sept/19100%


COMPLETED


Release date anticipated from 11th Nov to 16th Sept
Domibus 4.1.217/Sep/1929/Nov/1982%


ONGOING


Release date and scope redefined follow the anticipation of the 4.1.1 release

Domibus 4.2 RC

12/Nov/1921/Sep/207.5%

ONGOING


Domibus 4.2 FR22/Sep/2010/Dec/20-

NOT STARTED


SML 4.0 RC26/Nov/1815/May/19100%

COMPLETED

Postponed from the 21st Jan to the 15 May as agreed in a previous OMB
SML 4.0 FR16/May/1917/Jun/19100%


COMPLETED



SML 4.0.118/Jun/192/Oct/19100%


COMPLETED


bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct
SMP 4.1.116/May/1910/Oct/19100%

COMPLETED

Bug fix release
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC30/Jul/1801/Mar/19100%

COMPLETED


eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR04/Mar/1930/Apr/19100%

COMPLETED


wildfly and mysql
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC03/May/1920/Feb/2073%

ONGOING

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR20/Feb/2031/Mar/20-

NOT STARTED

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations

 Operations

Incident Management:


Operations management: