DOMIBUS:.
- Activities for release 4.1.2, planned for , following the scope adjustment required due to the anticipation of the release of 4.1.1 are progressing at the expected pace. Concurrently the work on version 4.2 has also been initiated.
SMP:
- Bugfix release 4.1.1 (SMP authentication improvement with CRL and CA | Improve handling shared keystore in Cluster environment | Bug fixing) was successfully released on the .
SML:
- SML 4.0.1 bug fix was released in acceptance on the as planned. And following the extra time required by the Data Center to set up the Production environment according to the new security standards to be adopted (https implementation) this version was released in production on the
eTrustEx adapter replacement Access Point plugin:
- Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) ongoing (FR ). Focus on assisting the entities using the adapter with the migration process to the eDelivery Acc Point - eTrustEx Plugin, seven onboarding process are ongoing at this stage, and on providing training to the SO.
- Meeting with the Portuguese Assembleia da Republic took place on the
- Meeting with OP in Luxembourg to discuss the best approach to the migration of their adapter instance on the
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 82% | ONGOING | Release date and scope redefined follow the anticipation of the 4.1.1 release |
12/Nov/19 | 21/Sep/20 | 7.5% | ONGOING | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SML 4.0.1 | 18/Jun/19 | 2/Oct/19 | 100% | COMPLETED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 100% | COMPLETED | Bug fix release |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 73% | ONGOING | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 31/Mar/20 | - | NOT STARTED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |