703039867OVERALL STATUS:   YELLOW   

Date:   

Reporting Period:   to  


Project Owner (PO): DG CNECT

Business Manager (BM): Maya Madrid

Solution Provider (SP): DIGIT

Project Manager (PM): Bogdan Dumitriu

Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.7

100%

COMPLETED

Security fix release

Domibus 5.1.1

100%

COMPLETED

Release date postponed from the - due to last minute bug detected, which resolution confirmation requires a quite complex testing scenario, testing which as been affected by another bug detected in the Domibus migration scripts. New release date will be communicated once the complex testing is executed.

Domibus 5.1.2

84%

IN PROGRESS

bug and security fix release

Domibus 5.2 RC

End Q1

62%

IN PROGRESS

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q2 2024

Q2 2024

0%

NOT STARTED

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q2 2024

Q3 2024

0%

NOT STARTED


Domibus 6.0 RC

Q3 2024

Q1 2025

0%

NOT STARTED


Domibus 6.0 FR

Q1 2025

Q2 2025

0%

NOT STARTED


DomiSML 4.3 FR

100%

COMPLETED

Anticipated form the  

DomiSML 5.0 RC

0%

NOT STARTED


DomiSML 5.0 FR

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.0.1

100%

COMPLETED


DomiSMP 5.1 RC

38%

IN PROGRESS


DomiSMP 5.1 FR

0%

NOT STARTED


eDelivery AS4 2.0 profile 

70%

IN PROGRESS

The main focus of this profile version is the upgrade to new cryptographic algorithms.

Public consultation started in June.

Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.

A new iteration of the specifications and a new public consultation will be necessary. The milestone and progress were updated to reflect this.

eDelivery SMP 2.0 profile

70%

IN PROGRESS

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

Public consultation started in June.

Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.

A new iteration of the specifications and a new public consultation will be necessary. The milestone and progress were updated to reflect this.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

40%

IN PROGRESS


Conformance testing service:  Extended coverage of eDelivery AS4 1.15 Common Profile

48%

IN PROGRESS


Migration to GITLab

Q4 202412%

ON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations

Q1 2024

84%

IN PROGRESS

Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer.

Updated completion date to Q1 2024 following the re-planning.


Newsroom account for eDelivery (for mailing list management)

?

10%

ON HOLD

Milestone will be considered completed when we have a newsroom with at least 1 newsletter approved by PO.
Update eDelivery projects & stakeholders repository

25%

IN PROGRESS

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
Overhaul of eDelivery communication materials

50%

IN PROGRESS

This includes the eDelivery tutorial, flyers, leaflet, PPT presentation materials.
Increase average online engagement rate to 15%

30%

ON HOLD

The current average engagement rate on Twitter is 5%. A change in the algorithm leads to a declining engagement rate as it favours payed-for accounts.

Ninth meeting of the Informal Cooperation Network for eDelivery (ICN) 

95%

IN PROGRESS

Post-event documentation and reimbursement are ongoing

eDelivery Interoperability Forum 28 November 2023

85%

IN PROGRESS

Post-event documentation ongoing 

Overall Project Progress

Technical

    • Public consultation of eDelivery AS4 2.0 and SMP 2.0 profiles ended on . Following feedback received for the consultation, an internal analysis was started and preliminary conclusions already suggest that:
      • the specifications will have to be modified in non-trivial ways and a new public consultation will be necessary, delaying the adoption by at least half a year.
      • an interoperability event will be organised to allow testing of pilot implementations of the new specifications in order to obtain technical validation.
    • Domibus 5.1.1 bug fix release was published on the 
    • Following a series of vulnerabilities discovered/reported:
      • Domibus 5.0.7 was released on the 
      • DomiSMP 5.0.1 was released on the  
      • Domibus 5.1.2 release planned for the 
    • Following successive issues reported by end users with upgrading the Domibus database when upgrading Domibus, a new process and approach was defined and implemented to provide more clarity and traceability about:
      • which scripts to use
      • which scripts were used before problems appeared
    • Domibus 5.2 & 6.0 release dates rescheduled for Q2 2024 and Q2 2025, respectively.

Onboarding & Communication

    • eDelivery Informal Cooperation Network (ICN) meeting held on  
    • eDelivery sample software represented at OSOR conference on in Brussels 
    • eDelivery Interoperability Forum held on  
    • eDelivery presentation at eFTI4EU event on and DTTF-eFTI meeting on  
    • The end of eDelivery public consultations on AS4 and SMP new technical specifications. Feedback received has been presented to the community during the eDelivery Interoperability Forum.

Technical Progress

Specifications: eDelivery AS4 & SMP Profiles

    • Advice from experts received in 2022 and 2023, respectively, was published as part of the consultation.
    • Following feedback received for the consultation, an internal analysis was started and preliminary conclusions already suggest that:
      • the specifications will have to be modified in non-trivial ways and a new public consultation will be necessary, delaying the adoption by at least half a year.
      • an interoperability event will be organised to allow testing of pilot implementations of the new specifications in order to obtain technical validation.
    • The eDelivery team will prepare and publish disposition of public review comments documents for both specifications in Q1 2024 and organise a meeting of Interoperability Forum to discuss them.
    • A written reply was received from the expert ENISA collaborates to the question raised by a solution provider regarding an increase in complexity in the cryptographic approach.

Software product: Domibus

    • Domibus 5.1.1 bug fix release was published on the 
    • Following the public communicated vulnerability in ActiveMQ, which is use in Domibus as a message broker, and vulnerabilities reported by a third party that conducted a security assessment to the eDelivery components,
      • Domibus 5.0.7 was released on the  (security instructions concerning the ActiveMQ vulnerability were provided to the user community beforehand)
      • Domibus 5.1.2 release planned for the 
    • Following successive issues reported by end users with upgrading the Domibus database when upgrading Domibus, a new process and approach was defined and implemented to provide more clarity and traceability about:
      • which scripts to use
      • which scripts were used before problems appeared
    • As communicated in the previous OMB, in light of the extensive work required for Domibus 5.0.6, 5.0.7 and 5.1.1, 5.1.2 patch releases, the review of the 2024-2025 roadmap was conducted, please see below:
      • Domibus 5.2 
        • RC: Q1 2024 (end)
        • FR: Q2 2024
      • Domibus 6.0
        • RC: Q1 2025
        • FR: Q2 2025

Software product: DomiSMP

    • Following the security assessment to the eDelivery components conducted by a third party DomiSMP 5.0.1 was released on  
    • DomiSMP 5.1 RC development activities are ongoing.

Software product: DomiSML

    • DomiSML 5.0 RC planned to be started on  

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

    • eDelivery AS4 1.15 profile enhancements conformance testing implementation:
      • Pull implementation on hold, due to the need for analysis work in some specific test cases
      • ENTSOG TCs implementation concluded
      • Dynamic Discovery Sender TCs implementation initiated
    • Analysis to strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products) is ongoing.
    • With the go-live of the platform and growing number of products undergoing the conformance process, the support work has increased substantially 

Software product: Docker images

    • Docker images for Domibus 5.1.x in a Tomcat + MySQL configuration – production readiness activities concluded. This is an OOTS requirement.
      • Domibus 5.1.1 corresponding image was published on the Domibus 5.1.1
    • Further work on the images was requested and is now underway with high priority given the go-live date of OOTS in December 2023.

Service: PKI Service

    • N/A

Service: SML Service

    • N/A

Section 2: Evolutive Maintenance

Change Requests

KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
EDELGOV-107Provide scripts for scheduled automated updates of PModes or Trust Stores
Request for Change
Nov 15, 2023Nov 28, 2023
Marcio SAMPAIOPim VAN DER EIJK
UNDER REVIEWUnresolved
EDELGOV-106Corruption when dropping empty (old) partitions on a live domibus

Request for Change

Oct 31, 2023Nov 29, 2023
Marcio SAMPAIOJoris Van den Bogaert
REJECTEDRejected
EDELGOV-105High value in domibus partitions are one off.

Request for Change

Oct 31, 2023Nov 29, 2023
Marcio SAMPAIOJoris Van den Bogaert
REJECTEDRejected
EDELGOV-104Domibus 5.1 does not cleanup the filestore with the PARTITIONS strategy

Request for Change

Oct 31, 2023Nov 29, 2023
Marcio SAMPAIOJoris Van den Bogaert
REJECTEDRejected
EDELGOV-103Domibus 5.1 does not drop empty partitions with the DEFAULT cleanup strategy

Request for Change

Oct 31, 2023Nov 29, 2023
Marcio SAMPAIOJoris Van den Bogaert
REJECTEDRejected
EDELGOV-92eDelivery growth factor by improved DNS recommendation of SML discovery
Request for Change
Dec 02, 2022Oct 23, 2023
Joze RIHTARSICGunnar Nilsson
UNDER REVIEWUnresolved
EDELGOV-89Fulfill the requirements on the BDEW AS4 Profile
Request for Change
Oct 28, 2022Sep 22, 2023
Cosmin BACIUSven Uthe
UNDER REVIEWUnresolved
EDELGOV-76Request for investigation of using multihop functionality with AS4
Request for Change
Nov 12, 2020Sep 28, 2022
Marcio SAMPAIOOle Vilstrup Møller


POSTPONEDOn hold
EDELGOV-51Dynamic Service discovery - SML/SMP change request

Request for Change

Sep 28, 2018Sep 22, 2023
Marcio SAMPAIOCIF VSRS

UNDER REVIEWUnresolved

Release Calendar

Section 3: Support Office

Incident Management

SMT - Workload Details

The volume of tickets and Jira issues remained quite stable in October 2023, compared to the previous months. Requests from users concern usual questions on Domibus and the different plugins, Domibus migration and migration scripts, AS4 connectivity test issues, conformance tests questions and issues, Domibus and Docker, etc.

Email Interaction

For eDelivery, received emails were related to:

  • Requests for AS4 connectivity test with RIMS
  • eDelivery conformance tests- questions from Opentext that is running the tests with the new GITB platform
  • PKI SOD for OOTS project finalised and sent
  • Request to use eDelivery SML services from a company working for the Polish Ministry of Digital Affairs – SML subdomain request form sent to customer - ongoing
  • Questions from users: Domibus (usage of plugins and plugin users, Domibus migration scripts to Domibus 5.0 and 5.1, compatibility with ActiveMQ Artemis, issue with Domibus start in Docker container, question on WS backend plugin), updated list of Peppol participants provided, SML/SMP (SMP/SMK certificate update/renewal,), PKI certificates (UDB, EPREL, BRIS, EUDAMED), TAPAS (Domibus 5.1.1 release and access to the Digital site only for TAPAS users, ICS2 connectivity test assistance requests (re-directed to the National service desks), onboarding request forwarded to National Helpdesk))
  • There was a total of 639 emails in the FMB. We have removed 66 emails for SML Inconsistency, 14 xmatters and 5 emails from PKI CommisSign from the count, which makes a total of 554 received mails for the reporting month.

PKI

In October 2023, 3 certificates were issued: 1 for DECIDE, 1 for EPREL and one for EUDAMED.

Operations Management

SML – Availability

The achieved availability for SML1 was within the target for the month of October.