Date:
Attendees:
- Dietmar GATTWINKEL (DG)
- Bogdan DUMITRIU (BD)
- Marcio SAMPAIO (MS)
- Yves Meersmans (YM)
- Ines COSTA (IC)
- Ioannis TSILOGIANNIS (IT)
Project progress
DOMIBUS:.
- 4.1.4 version created to address several detected bugs. This version will be planned if we deem the fixes necessary for our stakeholders before the 4.2 release.
- 4.2 version development activities continue to progress.
- eDelivery-Blockchain integration activity initiated - EBSI kickoff meeting held on the 18th May.
SML:
- A new SML release, 4.0.3, is planned for(FR) - Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats
SMP:
- New SMP release, 4.2, is planned for (FR) - Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates
eTrustEx adapter replacement Access Point plugin:
- eDelivery Acc Point - eTrustEx Plugin 1.2 release is delayed. A transaction management issue was discovered & fixed in the plugins (push mode testing), non-critical issue identified and reported for Domibus (pull mode testing).
- Changes to the release packaging: complete documentation and closing outstanding activities. Target deadline: 30 May 2020.
- The migration process to the eDelivery Acc Point - eTrustEx Plugin, as been hampered by the COVID-19 predicament since most of the entities ceased their activities temporarily
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 100% | COMPLETED | Release date and scope redefined follow the anticipation of the 4.1.1 release |
Domibus 4.1.3 | 29/Nov/19 | 10/Feb/20 | 100% | COMPLETED | CXF upgrade (plugin and security issue) |
Domibus 4.1.4 | - | - | - | NOT STARTED | bug fix release not yet planned |
12/Nov/19 | 21/Sep/20 | 51% | ONGOING | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SML 4.0.1 | 18/Jun/19 | 2/Oct/19 | 100% | COMPLETED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct |
SML 4.0.2 | 29/Nov/19 | 18/Feb/20 | 100% | COMPLETED | code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way. |
SML 4.0.3 | 20/Oct/20 | 10/Nov/20 | - | NOT STARTED | Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 100% | COMPLETED | Bug fix release |
01/Jun/21 | 01/Jul/21 | - | NOT STARTED | Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 100% | COMPLETED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 22/May/20 | 95% | DELAYED | New release date: 30th May Release delayed from the 31st March to the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
Operations
Incident Management:
Operations management: