Date:

 

Project progress

DOMIBUS:.

  • 4.1.4 version created to address several detected bugs. This version will be planned if we deem the fixes necessary for our stakeholders before the 4.2 release.
  • 4.2 version development activities continue to progress.
  • eDelivery-Blockchain integration activity initiated - EBSI kickoff meeting held on the 18th May.

SML:

  • A new SML release, 4.0.3, is planned for(FR) - Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats

SMP:

  • New SMP release, 4.2, is planned for (FR)  - Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates

eTrustEx adapter replacement Access Point plugin:

  • eDelivery Acc Point - eTrustEx Plugin 1.2 release is delayed. A transaction management issue was discovered & fixed in the plugins (push mode testing), non-critical issue identified and reported for Domibus (pull mode testing). 
  • Changes to the release packaging: complete documentation and closing outstanding activities. Target deadline: 30 May 2020. 
  • The migration process to the eDelivery Acc Point - eTrustEx Plugin, as been hampered by the COVID-19 predicament since most of the entities ceased their activities temporarily  

 

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milestones progress:


Milestone Title

Start Date

End Date

% complete

Status 

Comments

Domibus 4.0.210/Dec/1811/Feb/19100%


COMPLETED



Domibus 4.1 RC24/Sep/1820/May/19100%

COMPLETED

Release date postponed from the 1st March to 20th May
Domibus 4.1 FR21/Mar/1931/Jul/19100%

COMPLETED

Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July
Domibus 4.1.101/Aug/1916/Sept/19100%


COMPLETED


Release date anticipated from 11th Nov to 16th Sept
Domibus 4.1.217/Sep/1929/Nov/19

100%


COMPLETED


Release date and scope redefined follow the anticipation of the 4.1.1 release
Domibus 4.1.329/Nov/1910/Feb/20

       100%

COMPLETED

CXF upgrade (plugin and security issue) 

Domibus 4.1.4---

NOT STARTED

bug fix release not yet planned

Domibus 4.2 RC

12/Nov/1921/Sep/2051%

ONGOING


Domibus 4.2 FR22/Sep/2010/Dec/20-

NOT STARTED


SML 4.0 RC26/Nov/1815/May/19100%

COMPLETED

Postponed from the 21st Jan to the 15 May as agreed in a previous OMB
SML 4.0 FR16/May/1917/Jun/19100%


COMPLETED



SML 4.0.118/Jun/192/Oct/19100%


COMPLETED


bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct
SML 4.0.229/Nov/1918/Feb/20      100%

COMPLETED

code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way.
SML 4.0.320/Oct/2010/Nov/20-

NOT STARTED

Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats
SMP 4.1.116/May/1910/Oct/19100%

COMPLETED

Bug fix release

SMP 4.2

01/Jun/2101/Jul/21-

NOT STARTED

Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC30/Jul/1801/Mar/19100%

COMPLETED


eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR04/Mar/1930/Apr/19100%

COMPLETED


wildfly and mysql
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC03/May/1920/Feb/20100%

COMPLETED

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR20/Feb/2022/May/2095%

DELAYED

New release date: 30th May

Release delayed from the 31st March to the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations

 Operations

Incident Management:


Operations management: