Date: 

 

Attendees

Project progress

DOMIBUS:

  • Activities on version 4.1 RC (Support of Large files -Split and Join | Interface with UUM&DS and STI | EU Login support | ...) are ongoing and at pace for the code freeze date of the 12th April.
  • It was decided to schedule the 4.1.1 release (Encryption of stored messsages on the AP DB) with the goal of implementing a security control with the goal of facilitating the resource sourcing for the SO

SMP:

  • Preparation and adjustments to the component for the SHS migration ongoing

SML:

  • Activities on the SML 4.0 Acceptance release are progressing at the expected pace. Development conclusion projected for the 1st April.

eTrustEx adapter replacement Access Point plugin:

  • The setting up of the SHS environments for the eTrustEx adapter replacement Access Point plugin EC instance is completed for ACC and for PROD
  • Activities for the 1.1 RC concluded. Testing of the RC version ongoing

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milestones progress:


Milestone Title

Start Date

End Date

% complete

Status 

Comments

Domibus 4.0.210/Dec/1811/Feb/19100%


COMPLETED



Domibus 4.1 RC24/Sep/1820/May/1993%

ONGOING

Release date postponed from the 1st March to 20th May
Domibus 4.1 FR04/Mar/1924/May/19-

NOT STARTED

Release date postponed from the 24th May to 15th July
Domibus 4.1.116/Jul/1911/Nov/19-

NOT STARTED


Domibus 4.2 RC

16/Jul/1921/Sep/20-

NOT STARTED


Domibus 4.2 FR22/Sep/2010/Dec/20-

NOT STARTED


SML 4.0 RC26/Nov/1815/May/1981%

ONGOING

Postponed from the 21st Jan to the 15 May as agreed in a previous OMB
SML 4.0 FR22/Jan/1921/Feb/19-

NOT STARTED


eTrustEx adapter replacement Access Point plugin 1.1 RC30/Jul/1801/Mar/19100%

COMPLETED


eTrustEx adapter replacement Access Point plugin 1.1 FR04/Mar/1930/Apr/19100%

COMPLETED