Date:
Project progress
DOMIBUS:.
- 4.2 version development activities continue to progress at good pace.
SML:
- The SML release, 4.0.3, ( planned for(FR) - Security features and updates | Upgrade libraries to latest possible versions and fix OWASP threats) activities are progressing at good pace.
Rest API:
- Alignment of APIs4IPS meeting with JRC held on the
- Scoping document activities ongoing
Blockchain
- Discussion ongoing regarding the implementation of blockchain - time stamping and stats. Assistance requirements from the eDelivery DEV team to the process is being prepared.
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 100% | COMPLETED | Release date and scope redefined follow the anticipation of the 4.1.1 release |
Domibus 4.1.3 | 29/Nov/19 | 10/Feb/20 | 100% | COMPLETED | CXF upgrade (plugin and security issue) |
Domibus 4.1.4 | - | - | - | NOT STARTED | bug fix release not yet planned |
12/Nov/19 | 21/Sep/20 | 70% | ONGOING | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SML 4.0.1 | 18/Jun/19 | 2/Oct/19 | 100% | COMPLETED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct |
SML 4.0.2 | 29/Nov/19 | 18/Feb/20 | 100% | COMPLETED | code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way. |
SML 4.0.3 | 20/Oct/20 | 10/Nov/20 | 76% | ONGOING | Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 100% | COMPLETED | Bug fix release |
01/Jun/21 | 01/Jul/21 | - | NOT STARTED | Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 100% | COMPLETED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 8/Jun/2020 | 100% | COMPLETED | Release date: 8th June Release delayed from the 31st March to the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |