Date:

 

Attendees:


Project progress

DOMIBUS:.

  • Due to a detected CXF bug and consequent vulnerability issues, the bug fix release 4.1.3 will be released on the 10 Feb. In parallel the 4.2 development activities continue to progress

SML:

  • Following the extensive testing  conducted to ensure that the component can cope with the around 1.5 million records that BE (in the context of PEPPOL) will add to the EC SML instance, a new version, 4.0.2, is being developed. Development and testing activities for this version have been concluded and it was released in ACC on the 31st Jan. Prod release planned for the 18th Feb.

eTrustEx adapter replacement Access Point plugin:

  • Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) ongoing  (FR  ) is ongoing.  Focus on assisting the entities using the adapter with the migration process to the eDelivery Acc Point - eTrustEx Plugin, seven onboarding process are ongoing at this stage, and on providing training to the SO.

 

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milestones progress:


Milestone Title

Start Date

End Date

% complete

Status 

Comments

Domibus 4.0.210/Dec/1811/Feb/19100%


COMPLETED



Domibus 4.1 RC24/Sep/1820/May/19100%

COMPLETED

Release date postponed from the 1st March to 20th May
Domibus 4.1 FR21/Mar/1931/Jul/19100%

COMPLETED

Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July
Domibus 4.1.101/Aug/1916/Sept/19100%


COMPLETED


Release date anticipated from 11th Nov to 16th Sept
Domibus 4.1.217/Sep/1929/Nov/19

100%


COMPLETED


Release date and scope redefined follow the anticipation of the 4.1.1 release
Domibus 4.1.329/Nov/1910/Feb/20

       87%

ONGOING

CXF upgrade (plugin and security issue) 

Domibus 4.2 RC

12/Nov/1921/Sep/2020%

ONGOING


Domibus 4.2 FR22/Sep/2010/Dec/20-

NOT STARTED


SML 4.0 RC26/Nov/1815/May/19100%

COMPLETED

Postponed from the 21st Jan to the 15 May as agreed in a previous OMB
SML 4.0 FR16/May/1917/Jun/19100%


COMPLETED



SML 4.0.118/Jun/192/Oct/19100%


COMPLETED


bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct
SML 4.0.229/Nov/1918/Feb/20      98%

ONGOING

code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way.
SMP 4.1.116/May/1910/Oct/19100%

COMPLETED

Bug fix release
SMP 4.1.1 EC


NOT STARTED

to be planned
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC30/Jul/1801/Mar/19100%

COMPLETED


eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR04/Mar/1930/Apr/19100%

COMPLETED


wildfly and mysql
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC03/May/1920/Feb/2088%

ONGOING

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR20/Feb/2031/Mar/20-

NOT STARTED

making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations



 Operations

Incident Management:


Operations management: