Date

  

Attendees

Project progress


DOMIBUS:.

  • It was decided to delay the release of the 3.3.2 (support the upcoming EU FILE exchange monitoring tool) version for one month, in order to include in this release a fix for a bug detected in the File System plugin. 
  • Sluggish progress on the Domibus 4.0 (please find here the detailed scope) activities. The continuing  TAXUD ICS2 PoC and 3.3.2 activities are hampering the progress on 4.0. Furthermore the additional resources procured to address this situation have yet to initiate their collaboration with the project.
  • The TAXUD ICS2 PoC has been extended until friday the 9th March. This extension was agreed due to the delays experienced during the set up of the infrastructure, that prevented the testing to be conduct as planned. At the moment the load, stress and cryptographic tests have been executed. Failover and Pull test scenarios are ongoing.

SML:

SMP:

  •  SMP 4.0 RC ( Refactoring | SAD Software Architecture Document | COD Component offering Description | Audit trails | Bug fixes | security improvements implementation) was released on the 31st January, after being postponed due to the hacking of the edel test machines that prevented the testing activities to be conducted at its normal pace, and due to a major issue in ACC environment where the SMP and SML are deployed, the team responsible was forced to focus on the addressing this DC debacle. On the 26th February as scheduled the SMP 4.0 FR was released.

eTrustEx adapter replacement Access Point plugin RC:

  • ACC testing with DECIDE (core application) has been successfully concluded. The next step is to conduct the ACC testing with the eGreffe platform ( we are dependent on the availability of the eGreffe team to conduct the tests).

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milstones progress:

 Operations

Incident Management:

Operations management: