Call summary









 

Call updates
  • 16-10-2014 19:30:14

    16 October 2014:   Release 6 of the Question & Answers document has been published in the Additional Documents Section.

     

    Also, please note that the following changes were made to this call on 01 October 2014:

    • The closing date of the call was extended by 3 weeks from 15 October to 05 November

    • The Q&A mailbox was re-opened and will accept questions until the end of Friday 03 October

    • The template for Part B.I was updated. The changed sections are indicated in red text.

    • The embedded tables in Part B.I are available also now as an Excel file in the download ZIP of templates.

    • A Model Consortium Agreement has been provided in the Information Package section

    • An extensive new version of the Question & Answers document is published in the Additional Documents Section

    • Form A has been updated to correct an error in the selection of the funding rate (70% vs 100%)

    • The page size limit for Part B.I has been increased from 50 to 70.

    To locate the Q&A document see the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    To download the Excel version of the Part B.I tables you need to enter the submission system and click on "Download Templates" on the screen called "Step 5 - Edit Proposal".

  • 01-10-2014 13:13:38

    The following changes were made to this call on 01 October 2014:

    • The closing date of the call was extended by 3 weeks from 15 October to 05 November

    • The Q&A mailbox was re-opened and will accept questions until the end of Friday 03 October

    • The template for Part B.I was updated. The changed sections are indicated in red text.

    • The embedded tables in Part B.I are available also now as an Excel file in the download ZIP of templates.

    • A Model Consortium Agreement has been provided in the Information Package section

    • An extensive new version of the Question & Answers document is published in the Additional Documents Section

    • Form A has been updated to correct an error in the selection of the funding rate (70% vs 100%)

    • The page size limit for Part B.I has been increased from 50 to 70.

    To locate the Q&A document see the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    To download the Excel version of the Part B.I tables you need to enter the submission system and click on "Download Templates" on the screen called "Step 5 - Edit Proposal".

  • 01-10-2014 11:30:17

    The following changes were made to this call on 01 October 2014:

    • The closing date of the call was extended by 3 weeks from 15 October to 05 November
       
    • The Q&A mailbox was re-opened and will accept questions until the end of Friday 03 October
       
    • The template for Part B.I was updated. The changed sections are indicated in red text.
       
    • The embedded tables in Part B.I are available also now as an Excel file in the download ZIP of templates.
       
    • A Model Consortium Agreement has been provided in the Information Package section
       
    • An extensive new version of the Question & Answers document is published in the Additional Documents Section
       
    • Form A has been updated to correct an error in the selection of the funding rate (70% vs 100%)
       
    • The page size limit for Part B.I has been increased from 50 to 70.

    To locate the Q&A document see the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    To download the Excel version of the Part B.I tables click on the "Download all Documents" button in the "CALL DOCUMENTS" section.  You will find the Excel file in the ZIP.

  • 12-09-2014 19:13:08

    Release 4 of the Question and Answers document was uploaded to this web site on 12 September. It is available at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    New questions can still be submitted until 15 September for the next release of this document.

    The link to the CSJU Model Grant Agreement, which is in the topic documents section, is now also provided in the call documents section alongside the link to the annotated grant agreement for convenience.

    Also, as a reminder, the standard proposal template was also revised recently and is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents”.

    The updates regard the following paragraphs of part B:
    • 1.6 Complementary activities;
    • 3.4 Risk management

    As a result the following tables were revised to reflect these changes:
    • Table 3.1.a – List of Work Packages
    • Table 3.1.b – Work Package Descriptions
    • Table 3.1.c – Work Package Effort
    • Table 3.2 – List of identified critical risks and the mitigating measures foreseen
    • Table 3.3 – Budget summary

    Finally, note that the “annotated Grant Agreement” has been added to the full set of documents available for download under the tab “call documents” and in the section of Additional Documents of each topic under the tab "Topic Conditions and Documents”.
    This document might be useful for applicants looking for further explanations on articles of the Model Grant Agreement.

  • 05-09-2014 15:18:59

    Release 3 of the Question and Answers document was uploaded to this web site on 05 September. It is available at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    New questions can still be submitted until 15 September for the next release of this document.

    The link to the CSJU Model Grant Agreement, which is in the topic documents section, is now also provided in the call documents section alongside the link to the annotated grant agreement for convenience.

    Also, as a reminder, the standard proposal template was also revised recently and is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents”.

    The updates regard the following paragraphs of part B:
    • 1.6 Complementary activities;
    • 3.4 Risk management

    As a result the following tables were revised to reflect these changes:
    • Table 3.1.a – List of Work Packages
    • Table 3.1.b – Work Package Descriptions
    • Table 3.1.c – Work Package Effort
    • Table 3.2 – List of identified critical risks and the mitigating measures foreseen
    • Table 3.3 – Budget summary

    Finally, note that the “annotated Grant Agreement” has been added to the full set of documents available for download under the tab “call documents” and in the section of Additional Documents of each topic under the tab "Topic Conditions and Documents”.
    This document might be useful for applicants looking for further explanations on articles of the Model Grant Agreement.

  • 02-09-2014 13:39:33

    Release 2 of the Question and Answers document was uploaded to this web site on 02 September. It is available at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    New questions can still be submitted until 15 September for the next release of this document.

    Also, as a reminder, the standard proposal template was also revised recently and is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents”.

    The updates regard the following paragraphs of part B:
    • 1.6 Complementary activities;
    • 3.4 Risk management

    As a result the following tables were revised to reflect these changes:
    • Table 3.1.a – List of Work Packages
    • Table 3.1.b – Work Package Descriptions
    • Table 3.1.c – Work Package Effort
    • Table 3.2 – List of identified critical risks and the mitigating measures foreseen
    • Table 3.3 – Budget summary

    Finally, note that the “annotated Grant Agreement” has been added to the full set of documents available for download under the tab “call documents” and in the section of Additional Documents of each topic under the tab "Topic Conditions and Documents”.
    This document might be useful for applicants looking for further explanations on articles of the Model Grant Agreement.

  • 29-08-2014 11:41:58

    The standard proposal template has been revised and is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents”.

    The updates regard the following paragraphs of part B:
    • 1.6 Complementary activities;
    • 3.4 Risk management

    As a result the following tables were revised to reflect these changes:
    • Table 3.1.a – List of Work Packages
    • Table 3.1.b – Work Package Descriptions
    • Table 3.1.c – Work Package Effort
    • Table 3.2 – List of identified critical risks and the mitigating measures foreseen
    • Table 3.3 – Budget summary

    Finally, note that the “annotated Grant Agreement” has been added to the full set of documents available for download under the tab “call documents” and in the section of Additional Documents of each topic under the tab "Topic Conditions and Documents”.
    This document might be useful for applicants looking for further explanations on articles of the Model Grant Agreement.

  • 22-08-2014 12:16:31

    Template Part B. I of the applicant proposal has been revised and is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents”.

    The updates regard the following paragraphs:
    • 1.6 Complementary activities;
    • 3.4 Risk management

    As a result the following tables were revised to reflect these changes:
    • Table 3.1.a – List of Work Packages
    • Table 3.1.b – Work Package Descriptions
    • Table 3.1.c – Work Package Effort
    • Table 3.2 – List of identified critical risks and the mitigating measures foreseen
    • Table 3.3 – Budget summary

    Finally, note that the “annotated Grant Agreement” has been added to the full set of documents available for download under section “call document” and under section 6 of each topic under the tab "Topic Conditions and Documents”.
    Indeed, the CSJU concluded that this document might be useful for applicants looking for further explanations on articles of the Model Grant Agreement.
     

    The submission session is now available for: JTI-CS2-CPW-AIR-01-01(CS2-IA), JTI-CS2-CPW-AIR-01-02(CS2-IA), JTI-CS2-CPW-AIR-02-01(CS2-IA), JTI-CS2-CPW-AIR-02-02(CS2-IA), JTI-CS2-CPW-AIR-02-03(CS2-IA), JTI-CS2-CPW-AIR-02-04(CS2-IA), JTI-CS2-CPW-ENG-01-01(CS2-IA), JTI-CS2-CPW-ENG-01-02(CS2-IA), JTI-CS2-CPW-ENG-01-03(CS2-IA), JTI-CS2-CPW-ENG-02-01(CS2-IA), JTI-CS2-CPW-ENG-02-02(CS2-IA), JTI-CS2-CPW-ENG-03-01(CS2-IA), JTI-CS2-CPW-ENG-03-02(CS2-IA), JTI-CS2-CPW-ENG-04-01(CS2-IA), JTI-CS2-CPW-FRC-02-01(CS2-IA), JTI-CS2-CPW-FRC-02-02(CS2-IA), JTI-CS2-CPW-LPA-01-01(CS2-IA), JTI-CS2-CPW-LPA-01-02(CS2-IA), JTI-CS2-CPW-LPA-01-03(CS2-IA), JTI-CS2-CPW-LPA-01-04(CS2-IA), JTI-CS2-CPW-LPA-01-05(CS2-IA), JTI-CS2-CPW-LPA-01-06(CS2-IA), JTI-CS2-CPW-LPA-02-01(CS2-IA), JTI-CS2-CPW-LPA-02-02(CS2-IA), JTI-CS2-CPW-REG-01-01(CS2-IA), JTI-CS2-CPW-REG-01-02(CS2-IA), JTI-CS2-CPW-REG-02-01(CS2-IA), JTI-CS2-CPW-SYS-02-01(CS2-IA), JTI-CS2-CPW-SYS-03-01(CS2-IA)

  • 14-08-2014 15:59:59 The submission session is now available for: JTI-CS2-CPW-AIR-01-01(CS2-IA), JTI-CS2-CPW-AIR-01-02(CS2-IA), JTI-CS2-CPW-AIR-02-01(CS2-IA), JTI-CS2-CPW-AIR-02-02(CS2-IA), JTI-CS2-CPW-AIR-02-03(CS2-IA), JTI-CS2-CPW-AIR-02-04(CS2-IA), JTI-CS2-CPW-ENG-01-01(CS2-IA), JTI-CS2-CPW-ENG-01-02(CS2-IA), JTI-CS2-CPW-ENG-01-03(CS2-IA), JTI-CS2-CPW-ENG-02-01(CS2-IA), JTI-CS2-CPW-ENG-02-02(CS2-IA), JTI-CS2-CPW-ENG-03-01(CS2-IA), JTI-CS2-CPW-ENG-03-02(CS2-IA), JTI-CS2-CPW-ENG-04-01(CS2-IA), JTI-CS2-CPW-FRC-02-01(CS2-IA), JTI-CS2-CPW-FRC-02-02(CS2-IA), JTI-CS2-CPW-LPA-01-01(CS2-IA), JTI-CS2-CPW-LPA-01-02(CS2-IA), JTI-CS2-CPW-LPA-01-03(CS2-IA), JTI-CS2-CPW-LPA-01-04(CS2-IA), JTI-CS2-CPW-LPA-01-05(CS2-IA), JTI-CS2-CPW-LPA-01-06(CS2-IA), JTI-CS2-CPW-LPA-02-01(CS2-IA), JTI-CS2-CPW-LPA-02-02(CS2-IA), JTI-CS2-CPW-REG-01-01(CS2-IA), JTI-CS2-CPW-REG-01-02(CS2-IA), JTI-CS2-CPW-REG-02-01(CS2-IA), JTI-CS2-CPW-SYS-02-01(CS2-IA), JTI-CS2-CPW-SYS-03-01(CS2-IA)
  • 05-08-2014 12:07:00

    The Part B Template is now available for download in section 6 of each topic under the tab "Topic Conditions and Documents.

    An updated version of the Work Plan 2014-2015 has also been published. The only change is to the topic AIR-01-01.

    Contact details for the States Representative Group are now published under the "Get Support" Tab.

    All information to prepare a proposal is therefore available but the questions can still be submitted via the official channel in the get support section. Therefore applicants should check for future releases of the Q&A document. The facility for uploading proposals will be opened in due course.

    Just a reminder that 1 week ago:

    • Release 1 of the Questions & Answers document was published at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.
    • Misleading references to "Research and Innovation Actions" (RIA) were removed. All topics in this call are "Innovation Actions" (IA).
    • A problem with the link for downloading the Joint Technical Programme, which occured some time after the call publication, was fixed. This is a very large document and may take some time to download depending on the speed of your internet connection.
  • 30-07-2014 19:27:01

    Release 1 of the Questions & Answers document is now available at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    Misleading references to "Research and Innovation Actions" (RIA) have been removed from this call web site. All topics in this call are "Innovation Actions" (IA).

    A problem with the link for downloading the Joint Technical Programme, which occured some time after the call publication, has now been fixed. Please note that this is a very large document and therefore may take some time to download depending on the speed of your internet connection.

    The Part B Template, contact details for the States Representative Group and a modification to the topic AIR-01-01 will be published on this web site around the end of July. 
    Further release(s) of the Q & A document will also be published as required so potential applicants are advised to re-visit this web page periodically.

    By clicking on any one of the 29 topics listed below you will immediately see a short description of the topic.
    From there you can click on the adjacent tab  "Topic Conditions and Documents"  to see all relevant documents.

    In the document  "Clean Sky 2 JU Work Plan 2014 / 2015the full, detailed, topic descriptions begin after page 259 (Annex I).

  • 30-07-2014 19:22:32

    Release 1 of the Questions & Answers document is now available at the end of the "CALL DOCUMENTS" section. Just click on the "Call Documents" tab above and then scroll down.

    Misleading references to "Research and Innovation Actions" (RIA) have been removed from this call web site. All topics in this call are "Innovation Actions" (IA).

    The Part B Template, contact details for the States Representative Group and a modification to the topic AIR-01-01 will be published on this web site around the end of July. 
    Further release(s) of the Q & A document will also be published as required so potential applicants are advised to re-visit this web page periodically.

    By clicking on any one of the 29 topics listed below you will immediately see a short description of the topic.
    From there you can click on the adjacent tab  "Topic Conditions and Documents"  to see all relevant documents.

    In the document  "Clean Sky 2 JU Work Plan 2014 / 2015the full, detailed, topic descriptions begin after page 259 (Annex I).

  • 14-07-2014 11:31:28

    By clicking on any one of the 29 topics listed below you will immediately see a short description of the topic.
    From there you can click on the adjacent tab  "Topic Conditions and Documents"  to see all relevant documents.

    In the document  "Clean Sky 2 JU Work Plan 2014 / 2015the full, detailed, topic descriptions begin after page 259 (Annex I).

  • 10-07-2014 21:44:38

    By clicking on any one of the 29 topics listed below you will immediatly see a short description of the topic.
    From there you can click on the adjacent tab  "Topic Conditions and Documents"  to see all relevant documents.

    In the document  "Clean Sky 2 JU Work Plan 2014 / 2015the full, detailed, topic descriptions begin after page 259 (Annex I).

  • 10-07-2014 21:27:40

    .

Topics and submission service

To access the Submission Service, please select the TOPIC of your interest and then open the Submission Service tab.
To access existing draft proposals, please login to the portal and select My Proposals from the My Area menu.

In H2020, a proposal is submitted to a specific topic. The full set of information for preparing a proposal for a topic (eligibility and evaluation conditions, proposal templates, evaluation forms, etc.) is available on the topic conditions page. Select a topic from the call description page or go to Search Topics.

Download all documents
(EN only, incl. the additional docs.)

  • The full set of documents can be accessed via the links under each individual topic. Only the most important general documents are listed below.
  • Model Consortium Agreement en
  • Horizon 2020 Annotated Model Grant Agreement en
  • Clean Sky 2 JU Model Grant Agreement for Members en
  • Rules for submission, evaluation, selection, award and review procedures of Calls for Core Partners en
  • Clean Sky 2 Joint Undertaking Work Plan 2014 - 2015 en
  • Release 6 of the Questions and Answers Document: 16 October 2014 en

Clean Sky 2 Helpdesk:  Info-Call-CPW-2014-01@Cleansky.EU

Clean Sky 2 National Contact Points - Clean Sky 2 JU States Representative Group

Participant Portal FAQ – Submission of proposals

National Contact Points (NCP)

Enterprise Europe Network – national contact points' advice to businesses with focus on SMEs. The support includes guidance on the EU research funding.

Research Enquiry Service – ask questions about any aspect of European research and EU R&I programmes

IT Helpdesk – contact the IT helpdesk for questions such as forgotten passwords, access rights and roles, technical aspects of submission of proposals, etc.

Ethics – for compliance with ethical issues, see the Participant Portal and Science and Society Portal

European IPR Helpdesk assists you on intellectual property issues

The European Charter for Researchers and the Code of Conduct for their recruitment

CEN and CENELEC, the European Standards Organisations, advise you how to tackle standardisation in your project proposal. Contact CEN-CENELEC Research Helpdesk at research@cencenelec.eu.

Partner Search Services help you find a partner organisation for your proposal

H2020 Online Manual your online guide on the procedures from proposal submission to managing your grant