Preparation of the preliminary design, pre-investment study, environmental report, environmental impact report and geodesy for construction of the second track on the MariborŠentilj section of the railway line and upgrading of the existing track

Programme:

This project covers the preparatory studies for the upgrade of the existing track and construction of a second track on the Maribor-Šentilj railway line. The studies involve the environmental impact assessment, geodesy survey, and preliminary design elaboration. The outcomes will be used as a basis for the next planning and design steps before the construction works are started.

 

Once the section between both Slovenian cities is complete, an important bottleneck will be eliminated thanks to increased capacity of the line. This will facilitate passenger and freight traffic flows and foster further economic growth in the region.

 


 

State of progress on 31 December 2014:
The Action is ongoing. Elaboration of the pre-investment study and the preliminary design is in progress.  

 

 

Budget: 

 

Project promoter:

 

€561,750

Total project cost covered by this Decision:
 

€1,123,500

Percentage of EU support:  

 

Studies: 50%

EU contribution: 

 

€561,750

 

Download the Info Sheet about this project

 

This project was also the subject of a press release issued by the Agency.

 

Click map to view enlarged version

Member States involved:

Slovenia

 

Implementation schedule:

Start date: March 2014

End date: December 2015

 

Beneficiary & Implementing body:

 Ministry of Infrastructure

 