Track bed works, Signaling and Telecomunication Facilities. Section Pk 3,1 a Pk 6,8. San Roque Mercancías. Railway Line Bobadilla-Algeciras
The Action consisted of track bed works, signalling and telecommunications facilities in the section from the pk 3.1 to the pk 6.8 San Roque Mercancías, belonging to the conventional Bobadilla-Algeciras line, part of Priority Project 16 (Freight railway axis Sines/Algeciras-Madrid-Paris). The works included inter alia the: i) complete renovation of the existing single track in Iberian gauge, by laying down polyvalent sleepers; ii) installation of a Centralised Traffic Control (CTC) system; iii) construction of small variants and rail side track; iv) curve corrections and embankment stabilisation, v) reduction of the number of level crossings and v) power supply to equipment and facilities.
The Action contributed to increase the capacity of the line Bobadilla-Algeciras, improved its passenger and freight traffic conditions, in particular in the rail access to the port of Algeciras. Furthermore, it contributed to the implementation of Priority Project 16 by enhancing the competitiveness of the rail mode in the connections between the cities along the corridor Algeciras/Ronda/Bobadilla/Granada/Madrid, minimizing the environmental impact of the corridor and strengthening the territorial cohesion in Southwest Europe.
The action is closed.
EU contribution: €482,560 |
Download the Info Sheet about this project
Member States involved:
Spain
Implementation schedule:
Start date: March 2013
End date: December 2015
Beneficiary Implementing body:
Administrador de Infraestructuras Ferroviarias (ADIF)
Additional information:
European Commission, DG MOVE
Innovation and Networks Executive Agency (INEA)