Innovation and Networks Executive Agency

Rail 2007-EU-06010-P

New Lyon-Turin Rail Link - Franco-Italian Common Part of the International Section (Studies and Works)

Programme:

The new freight and passenger rail link between Lyon and Turin (Priority Project 6) will act as a key node between northern and southern Europe (London/Amsterdam/Paris-Milano) and west and east (Lisbon-Budapest). It will considerably shorten travel times for high speed passenger traffic and provide an environmentally friendly response to the steadily increasing demand for freight transport over the Alps.

 

This project concerns the common French-Italian part of the 80 km international section from Saint Jean de Maurienne to Sant'Antonino-Vaie in the Chiuse valley. The main lineside structures are the 57.1 km French-Italian "Base Tunnel" and 11.4 km Orsiera Tunnel on the Italian side.

 

The project includes technical design studies, environmental studies, realisation of descending shafts and galleries, preparation of the construction sites.

 


 

State of progress on 31 December 2014:

Geotechnical surveys at Modane, La Praz and Saint Martin la Porte descending shafts as well as monitoring activities at La Praz and Saint Martin la Porte (SMP) have been completed. Environment and geological studies at Maddalena gallery were carried out up to a length of 1900 metres. In France, land acquisition has started and is in progress, while the administrative order to start the geological inverstigation at Saint Martin la Porte gallery was signed. Project studies in France and final design studies in Italy were completed.

 

 

Budget:

 

National budget:

 

€489,503,225

 

 

 

Total project cost covered by this Decision:

 

€890,476,300

 

Percentage of EU support:

 

Studies: 50%


Works: Activity 11 (until 31/12/2011): 27%

Activity 11 (from 01/01/2012 until 31/12/2015): 30%

Activity 12: 27%

 

EU contribution:

 

€400,973,075

 

Download the Info Sheet about this project

 

This project was also looked at during the Mid-Term Review of the 2007-2013 TEN-T Multi-Annual Work Programme.

Click map to view enlarged version

Member States involved:

Italy, France

 

Implementation schedule:

Start date: January 2007

End date: December 2015

 

Beneficiaries:

French Republic

Italian Republic

 

Implementing body:

 Lyon Turin Ferroviaire SAS  

 

Additional information:

 European Commission, DG MOVE


 See projects by country or transport mode