Innovation and Networks Executive Agency

Rail 2005-IT-90901-S

New AV/AC line Venezia-Trieste-(Lubiana) in Italian territory: sections project

Programme:

The project concerns the preliminary design for high speed track of the railway section Venice-Trieste. In detail, are concerned the following subsections:

  • from Venice Mestre to the underground Venice Airport station and Quarto d'Altino
  • from Venice Santa Lucia to Venice Airport
  • from the underground Venice Airport station to Bivio Dese

The project, closely correlated with project 2004-IT-90905-S concerning other sections on the same alignment, is part of the Priority Project 6 (Railway axis Lyon-Trieste-Divaca/Koper-Divaca-Ljubljana-Budapest-Ukranian border). As such, it contributes to shorten travel times for high speed passenger traffic.

 


 

This project has been completed.

 

Budget:

 

National budget:

 

€2,500,000

Total project cost covered by this Decision:

 

€4,500,000

Percentage of EU support:

 

Studies: 44.4%

EU contribution:

 

€2,000,000

 

Download the Info Sheet about this project:

 .pdf (369.6 KB)

 

Click map to view enlarged version

Member States involved:

Italy

 

Implementation schedule:

Start date: December 2005

End date: December 2010

 

Beneficiary:

 Republic of Italy

 

Implementing body:

 Ferrovie dello Stato S.p.A.

 

Additional information:

 European Commission, DG MOVE


 See projects by country or transport mode