Innovation and Networks Executive Agency

Rail 2007-HU-06100-S

Studies for preparation of approval of the railway line section Budapest-Keleti-Miskolc-Nyiregyhaza

Programme:

This project aims at upgrading the 262 km railway line between Budapest Rakos station (excluded) and Nyiregyhaza stations (excluded), part of Priority Project 6 (railway axis Lyon-Trieste-Divaèa/Koper-Divaèa-Ljubljana-Budapest-Ukrainian border). The project will enhance rail freight transport as well as improve local passenger service quality in terms of time savings and operating and maintenance costs.

 

The project encompasses the three following activities:

  1. Geodetic and geotechnical survey;
  2. Preparation of designs for approval of track, catenary, public lighting, switch heating, signalling system, telecommunications and structures and traffic plans, and
  3. Environmental impact assessment (EIA) study.

 

This project has been completed.

 

Budget:

 

National budget:

 

€6,550,496

Total project cost covered by this Decision:

 

€13,100,993

Percentage of EU support:  

 

Studies: 50%

EU contribution: 

 

€6,550,496

 

Download the Info Sheet about this project

 

This project was also looked at during the Mid-Term Review of the 2007-2013 TEN-T Multi-Annual Work Programme.

Click map to view enlarged version

Member States involved:

Hungary

 

Implementation schedule:

Start date: March 2009

End date: December 2013

 

Beneficiary & Implementing body:

 National Infrastructure Development Company

 

Additional information:

 European Commission, DG MOVE