Innovation and Networks Executive Agency

Rail 2004-HU-92203-S

Study on the rehabilitation of the railway line section Székesfehérvár-Boba

Programme:

This project, part of Priority Project 6 (railway axis Lyon-Trieste-Divaèa-Koper-Divaèa-Ljubljana-Budapest-Ukranian border), involves studies for the upgrading of the railway track Székesfehérvár-Boba to a speed of 120/140 km/h. The project also aims at improving traffic management and safety aspects.

 

The project main activity is the preparation of the technical design for approval, including railway track design, preliminary general plan, bridges, tunnels and subways, electric overhead line, signaling and telecommunications, public lighting, building and environmental impact assessment study.

 


 

This project has been completed.

 

Budget:

 

National budget:

 

€3,000,000

Total project cost covered by this Decision:

 

€5,000,000

Percentage of EU support:

 

Studies: 40%

EU contribution:

 

€2,000,000

 

Download the Info Sheet about this project:

 .pdf (514.3 KB)

 

Click map to view enlarged version

Member States involved:

Hungary

 

Implementation schedule:

Start date: January 2005

End date: December 2008

 

Beneficiary:

 Ministry of Economy and Transport

 

Implementing body:

 Hungarian State Railways Co. (MÁV Co.)

 

Additional information:

 European Commission, DG MOVE


 See projects by country or transport mode