Study on the rehabilitation of the railway line section Szajol-Záhony

Programme:

This project, part of Priority Project 6 (railway axis Lyon-Trieste-Divaca-Koper-Divaca-Ljubljana-Budapest-Ukranian border), involves studies for the upgrading of the railway track Szajol-Záhony to a speed of 160 km/h, double track and electric traction. The project also aims at enhancing traffic management and passenger safety.

 

The project encompasses the following activities:

  • Preparation of the design for approval for the section Szajol-Püspökladány;
  • Preparation of the design for approval for the section Püspökladány- Nyíregyháza;
  • Preparation of the design for approval for the section Nyíregyháza-Záhony
  • Preparation of ETCS signaling design, tender documentation and substations feasibility study for the whole line.

 

This project has been completed.

 

Budget:

 

National budget:

 

€12,000,000

Total project cost covered by this Decision:

 

€18,000,000

Percentage of EU support:

 

Studies: 33.33%

EU contribution:

 

€6,000,000

 

Download the Info Sheet about this project:

 .pdf (124.3 KB)

 

Click map to view enlarged version

Member States involved:

Hungary

 

Implementation schedule:

Start date: December 2004

End date: December 2008

 

Beneficiary:

 Ministry of Economy and Transport

 

Implementing body:

 Hungarian State Railways Co. (MÁV Co.)

 