Innovation and Networks Executive Agency

Rail 2007-BE-28050-P

INEA ceased operations on 31 March 2021. The European Climate, Infrastructure and Environment Executive Agency (CINEA) was established on 1 April 2021 to take over its legacy portfolio as well as additional EU funding programmes.

Euro Cap Rail on the Brussels-Luxembourg-Strasbourg railway axis

Programme:

This project, part of the Priority Project 28 (EuroCap-Rail: Brussels-Luxembourg-Strasbourg railway axis), aimed to modernise and improve the existing railway between Brussels and the Luxembourg border to allow a significant increase in train speed and therefore a large reduction in travel time.

This project concerned a 226 km section from Brussels to Luxembourg. Works were mainly focused on:

  • reducing the most burdensome curves which currently posed one of the major obstacles to higher operating speeds,
  • regularising the track spacing at 2.25 m to allow a design speed of 160 km/h,
  • adapting structures which were affected by the new track spacing,
  • modernising various railway stations.

This project improved comfort, safety and travel time for passengers travelling between the North Sea, France, Luxembourg, Switzerland, Germany or Italy through Belgium.   


The Action is closed

 

EU contribution: €13,294,347

 

Download the Info Sheet about this project

 

This project was also looked at during the Mid-Term Review  of the 2007-2013 TEN-T Multi-Annual Work Programme.

Click map to view enlarged version

Member States involved:

Belgium

Implementation schedule:

Start date: January 2007
End date: December 2015

Beneficiary & Implementing body:
 Infrabel

Additional information:

 European Commission, DG MOVE
 Innovation and Networks Executive Agency (INEA)​

 


 See projects by country or transport mode