EuroAsia Interconnector - Final Detailed Studies

3.10.1-0004-CYEL-S-M-16

The Action contributes to the implementation of the cluster of projects of common interest 3.10. The EuroAsia Interconnector consists of a 500 kV DC underwater electric cable and associated equipment for interconnecting the Cypriot, Israeli and Greek transmission networks. The first phase of the interconnector will have a capacity of 1,000 MW and a total length of around 1,518 km.

 

Building upon the preparatory studies financed under CEF Action 3.10.1-0028-CY-S-M-14, the objective of this Action is to finalise the design of the interconnector and to procure the associated works contracts. The scope entails the Detailed Geophysical and Geotechnical Route Study; the Submarine Power Cable Installation Study; the Territorial Civil Works Study; the Front End Engineering Design Study; and procurement consultancy services.

 

Upon completion of the Action, the construction of the PCIs will be launched.

 

The Action will start in June 2017.

 

 

Estimated cost of the action: €29,000,000 Percentage of EU support:  50%
Maximum EU contribution: €14,500,000

 

Download the Info Sheet about this project:

/inea/en/file/3.10.1-0004-cyel-s-m-16actionfiche.pdf.pdf

 

Please note that the present document is for information purposes only. The content and conditions of the grant agreement always prevail over any different information which may be included in this document or elsewhere.

Member States involved:

Cyprus, Greece

 

Implementation schedule:

Start date: June 2017

End date: December 2020

 

Beneficiary(ies):

 EuroAsia Interconnector Limited

 

Additional information:

 European Commission, DG ENER

 Agency for the Cooperation of Energy Regulators (ACER)

 European Network of Transmission System Operators for Electricity (ENTSO-E)

 