Innovation and Networks Executive Agency

Construction of LNG terminal Krk

Programme: 
CEF Energy
Call year:
Member State(s):
Implementation schedule: 
February 2018 to December 2019
Maximum EU contribution: 
€101,400,000
Estimated total cost: 
€363,180,516
Percentage of EU support: 
28%
Beneficiaries: 
LNG Hrvatska d.o.o.
Status:
Energy corridor:
Energy sector:
Project(s) of Common Interest:
Additional information: 

European Commission, DG ENER
http://ec.europa.eu/energy/en/topics/infrastructure

Agency for the Cooperation of Energy Regulators (ACER)
http://www.acer.europa.eu/

European Network of Transmission System Operators for Gas (ENTSOG)
http://www.entsog.eu/

Last modified: 
February 2018

6.5.1-0018-HR-W-M-16

The Action implements the first phase of the project of common interest (PCI) 6.5.1, which consists of the phased development of a liquefied natural gas (LNG) terminal on the island of Krk in Croatia. The objective of the Action is to procure and put into operation a permanently moored Floating Storage and Regasification Unit (FSRU) and to construct a dedicated jetty and a connecting pipeline with an approximate send-out capacity of 2 bcm/year. The investments will form an integrated facility to unload, store and regasify LNG and will allow for anchoring special purpose LNG vessels, refilling LNG into the tanks, storing and reloading. The regasification plant of the terminal will allow for supplying regasified natural gas to the national gas grid system. The reloading facility of the terminal will enable refilling of liquefied natural gas to the smaller special purpose LNG vessels.

The completion of the Action will enhance the diversification of natural gas supply for Central Eastern & South Eastern Europe, it will increase security of gas supply, improve competitiveness in the region and provide for a more effective integration of key infrastructure projects like the North-South Gas Interconnections in Central Eastern and South Eastern Europe into the European gas market.

The Action represents the next step in the PCI development, following the preparatory studies carried out under other CEF-funded actions (6.5.1-0037-HR-S-M-14, 6.5.1-0026-HR-S-M-15 and 6.5.1-0014-HR-S-M-16).

Beneficiary's website:

http://www.lng.hr