Date: 

 

Attendees


Project progress

DOMIBUS:.

  •  Version 4.1 FR (Support of Large files - Split and Join | Interface with UUM&DS and STI | EU Login support | ...) was released on the 31st July, as planned.
  • Activities on 4.1.1 initiated and progressing as scheduled.

SMP:

  •  bugfix release 4.1.1 on schedule (SMP authentication improvement with CRL and CA | Improve handling shared keystore in Cluster environment | Bug fixing)

SML:

  • SML 4.0.1 bug fix development is completed. Testing phase ongoing. Release is scheduled  in ACC on the  and in PROD on the  

eTrustEx adapter replacement Access Point plugin:

  • All the entities using the eTrustEx adapter were contacted in order to start the migration process. Meeting held with the Italian senate on the   | Meeting scheduled with the Committee of Regions on the  
  • Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) progressing. Release date yet to be defined. The focus will be directed at the migration process of the entities using the eTrustEx adapter instance. 

Evolutive Maintenance

Requests for change:


N/A



Release calendar:

For more details, please consult this page.



Milestones progress:



Milestone TitleStart DateEnd Date% completeStatus Comments
Domibus 4.0.210/Dec/1811/Feb/19100%


COMPLETED



Domibus 4.1 RC24/Sep/1820/May/19100%

COMPLETED

Release date postponed from the 1st March to 20th May
Domibus 4.1 FR21/Mar/1931/Jul/19100%

COMPLETED

Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July
Domibus 4.1.101/Aug/1911/Nov/19-

ONGOING


Domibus 4.2 RC

12/Nov/1921/Sep/20-

NOT STARTED


Domibus 4.2 FR22/Sep/2010/Dec/20-

NOT STARTED


SML 4.0 RC26/Nov/1815/May/19100%

COMPLETED

Postponed from the 21st Jan to the 15 May as agreed in a previous OMB
SML 4.0 FR16/May/1917/Jun/19100%


COMPLETED



SML 4.0.118/Jun/1918/Sep/1982%

ONGOING

bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod release 18th Sept
SMP 4.1.116/May/1910/Oct/1962%

ONGOING

Bug fix release
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC30/Jul/1801/Mar/19100%

COMPLETED


eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR04/Mar/1930/Apr/19100%

COMPLETED


wildfly and mysql
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC03/May/19TBD-

ONGOING


eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FRTBDTBD-

NOT STARTED







 Operations

Incident Management: