Date

  

Attendees


Project progress

 DOMIBUS:

  • The Domibus 3.3.1 bug fix release planned for the 5th December was released on the expected date. This version includes a number of bug fixes and improvements:
    • New API to retrieve a User Message
    • Implement a restricted account lockout policy in authentication mechanisms
    • Fix the move of JMS messages in a WebLogic cluster environment
    • Fixed an issue in the receipt generated in WildFly.
  • The work on the versions 3.3.1 and 3.3.2 (support the upcoming EU FILE exchange monitoring tool)  and the prolonged absence of some team members lead to the progress on the 4.0 release being slower than initially expected. Moreover, the assistance that will be provided to the ICS2 PoC will lead to a substantial delay on the 4.0 related activities

SML:

  • The work on the SML 4.0 RC was initiated, however during the preparation activities for the 2018 eDelivery roadmap it was decided to put this release on hold and opt for an intermediate release focused on security improvement, SML 3.1.2 (please find here the detailed scope). Moreover it will also include a request for change from the TOOP project (EDELGOV-37). The release of this version was postponed to the end of January in order to better align TOOP`s request with their actual needs.

SMP:

  • The activities  for SMP 4.0 RC ( Refactoring | SAD Software Architecture Document | COD Component offering Description | Audit trails | Bug fixes | security improvements implementation)  are currently ongoing with a slight delay. To be released on the 21st December, instead of the previously planned date, 15th December


eTrustEx adapter replacement Access Point plugin RC:

  • DECIDE project`s acceptance period was postponed at request of SecGen. A meeting to redefine the planning was held on the 8th December. It as agreed to conduct a pre-acceptance testing from January to February, followed by the full-blown acceptance testing from February to the end of March.

Evolutive Maintenance

Requests for change:


N/A



Release calendar:


For more details, please consult this page.



Milstones progress:

Milestone TitleStart DateEnd Date% completeStatus Comments
Domibus 3.2.307/Mar/17

30/Mar/17

100%

COMPLETED


Domibus 3.2.4

14/Mar/17

19/April/17

100%

COMPLETED


Domibus 3.2.5

2/May/17

9/June/17

100%

COMPLETED

Postponed from the 31st May to the 9th June.
Domibus 3.3 RC111/Oct/1630/Jun/17100%

COMPLETED

Release postponed from the 16th June to 30th June.
Domibus 3.3 FR23/Jun/176/Oct/17100%

COMPLETED


Release date postponed from the 22nd of September to the 6th Oct.
DOMIBUS 3.3.116/Oct/1705/Dec/17100%


COMPLETED

Hotfix release to address an issue raised by eJustice.
DOMIBUS 3.3.206/Dec/1712/Feb/1825%

ONGOING

functionalities to support the upcoming EU FILE exchange monitoring tool
Domibus 4.0 RC25/Sep/1716/Mar/1815%

ONGOING


Domibus 4.0 FR19/Mar/1818/May/18-

NOT STARTED


SML 3.0.116/Sep/1612/May/17100%

COMPLETED

Postponed from the 30th April to the 12th May

SML 3.1.1

02/Oct/1725/Oct/17100%

COMPLETED

Bug fix release
SML 3.1 RC18/Nov/1623/Jun/17100%

COMPLETED


SML 3.1 FR

26/JUN/1

24/July/17100%

COMPLETED


SML 3.1.2 Acceptance Release23/Oct/177/Feb/1760%

ONGOING

This release was postponed due to the lack of clarity of the TOOP project regarding the change request to be implemented. Release postponed from 18th Dec to 7th Feb in order to better align TOOP`s request with their actual needs.

SML 3.1.2 Acceptance Release7/Feb/1714/Feb/17-

NOT STARTED


SML 4.0 RC26/Jun/1728/Feb/1856%

ON HOLD


SML 4.0 FR02/Apr/1804/Jun/18-

ON HOLD


SMP 3.0 RC216/Feb/1718/May/17100%

COMPLETED

Bug fixing release - postponed from the 4th to the 18th May

SMP 3.0 FR18/May/1716/Jun/17100%

COMPLETED


SMP 3.0.121/Aug/177/Sept/17100%
COMPLETED
Release was postponed from the initially planed 30th August
SMP 3.0.202/Oct/1718/Oct/17100%

COMPLETED

Bug fix release
SMP 4.0 RC19/Jun/1721/Dec/1790%

DELAYED

Development slightly delayed due to team focus on multiple hotfixes releases for SMP and SML. Previously conclusion date 15th December


SMP 4.0 FR18/Dec/1719/Feb/18-

NOT STARTED


eTrustEx adapter replacement Access Point plugin RC20/Jan/171/Feb/1793%

ONGOING

Release postponed at request from SecGen. Planning was redefined in a meeting on the 8th December. The Acceptance test process with DECIDE will start in early January 2018
eTrustEx adapter replacement Access Point plugin FR01/Mar/1730/Apr/18

NOT STARTED