Date
Attendees
- Carlos GOMEZ MUNOZ (CGM)
- Adrien FERIAL (AF)
- Marcio SAMPAIO (MS)
- Sylwia SIGUR (SS)
- Alexandre Tombeur (AT)
- Ines COSTA (IC)
- Gregory STEENBEEK (GS)
Project progress
DOMIBUS:.
- 3.3.3 version was released, following a functionality request from the Greek Ministry - AP message self-send feature. And the timeline mismatch with the PEPPOL PKI support.
- Work on 3.3.4 version (Integrate the changes performed for Taxud | Improve the performance of the Messages page | Support the new PEPPOL PKI) is ongoing and should be released as planned at the end of May.
- Work version 4.0 is presenting a sluggish progress, due to the need of focusing effort on the 3.3.3 and 3.3.4 versions. Moreover the extending of the TAXUD PoC and the sudden departure of TO team members may further hinder the progress of the activities.
- The TAXUD ICS2 PoC was not yet concluded. The delays experienced during the set up of the infrastructure, and recurrent issues encountered that prevented the testing to be conduct as planned, led to extending the duration of the PoC. However, due to a infrastructural issue blocking the failover and pull stress tests execution, that IBM (TAXUD's contractor) has not been able to overcome it was decided to halt the execution of the remaining tests. Upon the resolution of this issue, it as agreed, that the testing activities will be continued by IBM and eDelivery TO will provide support if needed
SMP:
- Due to the sudden absence of the responsible for the component, due to the security clearance checks conducted by the EC the work on SMP 4.1 RC ( Admin Console | Improve audit logs to comply with the EU File exchange service monitoring tool | HTTPS used for all internal traffic in EC network) work has been put on hold.
eTrustEx adapter replacement Access Point plugin RC:
- ACC testing with eGreffe has been concluded, following the successfully testing with DECIDE. The next step is to conduct the end to end ACC testing by the DECIDE business.
Evolutive Maintenance
Requests for change:
N/A
Milstones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
DOMIBUS 3.3.1 | 16/Oct/17 | 05/Dec/17 | 100% | COMPLETED | Hotfix release to address an issue raised by eJustice. |
DOMIBUS 3.3.2 | 06/Dec/17 | 12/Feb/18 | 100% | COMPLETED | Release postpone due to a bug encountered and the decision to integrate a fix to a FS plugin issue. functionalities to support the upcoming EU FILE exchange monitoring tool functionalities to support the upcoming EU FILE exchange monitoring tool. |
Domibus 3.3.3 | 19/Mar/18 | 06/Apr/18 | 100% | COMPLETED | |
Domibus 3.3.4 | 02/Apr/18 | 20/Jun/18 | 70% | DELAYED | Integrate the changes performed for Taxud | Improve the performance of the Messages page | Support the new PEPPOL PKI Delayed from the 30th May to the 20th June |
Domibus 4.0 RC | 25/Sep/17 | 15/Aug/18 | 63% | DELAYED | Release date postponed from the 15th June to the 1st August |
2/Aug/18 | 21/Sep/18 | - | NOT STARTED | ||
SML 3.1.1 | 02/Oct/17 | 25/Oct/17 | 100% | COMPLETED | Bug fix release |
SML 3.1.2 Acceptance Release | 23/Oct/17 | 7/Feb/17 | 100% | COMPLETED | |
SML 3.1.2 Production Release | 7/Feb/17 | 07/Mar/18 | 100% | COMPLETED | |
SML 4.0 RC | 26/Jun/17 | 28/Feb/18 | 56% | ON HOLD | |
SML 4.0 FR | 02/Apr/18 | 04/Jun/18 | - | ON HOLD | |
SMP 3.0.2 | 02/Oct/17 | 18/Oct/17 | 100% | COMPLETED | Bug fix release |
SMP 4.0 RC | 19/Jun/17 | 31/Jan/18 | 100% | COMPLETED | |
SMP 4.0 FR | 18/Dec/17 | 26/Feb/18 | 100% | COMPLETED | |
SMP 4.1 RC | 27/Feb/18 | 30/Oct/18 | 11% | DELAYED | Postponed from the 18th April to the 30th October |
SMP 4.1 FR | 19/Apr/18 | 23/May/18 | - | DELAYED | Postponed from the 23rd May to the 30th November |
eTrustEx adapter replacement Access Point plugin RC | 31/Oct/17 | 30/May/18 | 98% | DELAYED | Release still postponed at request from SecGen. Acceptance testing ongoing in the DECIDE environment. There has been discrepancies between the information regarding the acc and prod environments between DECIDE and eGreffe. According to SecGen, after the acceptance test in DECIDE the same will have to be conducted in eGreffe. |
eTrustEx adapter replacement Access Point plugin FR | 01/Jun/17 | 26/Jun/18 | NOT STARTED |