Date
Attendees
- Serge NOVARETTI (SN) - Chair
- Adrien FERIAL (AF)
- Marcio SAMPAIO (MS)
- Clothilde WATTEL (CW)
- João NEVES (JN)
Project progress
DOMIBUS:
- During the current reporting period two intermediate DOMIBUS versions have been released:
- - 3.2.3_Hotfix |Fix on security for pMode upload |Fix for listPendingMessages
- - 3.2.4_Hotfix release fixing the backward compatibility issue detected by ODR
In parallel the activities related with the DOMIBUS 3.3 release are ongoing.
SML:
- SML 3.0.1 release will be concluded with a slight delay of a few days.
- In parallel the activities for the SML 3.1 release are ongoing, with a slightly slower pace then expected at this point.
SMP:
- The SMP 3.0 RC2 will be released on the 3rd May, according to with the activityg.
Evolutive Maintenance
Requests for change:
Milstones progress
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 3.2.3 | 07/Mar/17 | 30/Mar/17 | 100% | COMPLETED | |
Domibus 3.2.4 | 14/Mar/17 | 19/April/17 | 100% | COMPLETED | |
Domibus 3.2.5 | 2/May/17 | 30/May/17 | 0% | NOT STARTED | |
Domibus 3.3 RC1 | 11/Oct/16 | 16/Jun/17 | 68% | ONGOING | |
Domibus 3.3 FR | 23/Jun/17 | 22/Sep/17 | NOT STARTED | ||
Domibus 4.0 RC | 25/Sep/17 | 16/Mar/18 | NOT STARTED | (to be detailed RC1 and FR dates) | |
Domibus 4.0 FR | 19/Mar/18 | 18/May/18 | NOT STARTED | ||
SML 3.0.1 | 16/Sep/16 | 30/Apr/17 | 92% | DELAYED | revised expected completion date 10/May/17 |
SML 3.1 | 18/Nov/16 | 23/Jun/17 | 22% | DELAYED | |
SML 4.0 RC | 26/Jun/17 | 30/Mar/18 | NOT STARTED | ||
SML 4.0 FR | 02/Apr/18 | 04/Jun/18 | NOT STARTED | ||
SMP 3.0 RC2 | 16/Feb/17 | 03/May/17 | 79% | ONGOING | |
SMP 3.0 FR | 04/May/17 | 16/Jun/17 | NOT STARTED | There is a dependency with the eHealth project for the end date | |
SMP 4.0 RC | 19/Jun/17 | 15/Dec/17 | NOT STARTED | ||
SMP 4.0 FR | 18/Dec/17 | 19/Feb/18 | NOT STARTED |
Operations
Operations management:
Incident Management:
Operations management: