Date

  

Attendees


Project progress

DOMIBUS:

  • During the current reporting period two intermediate DOMIBUS versions have been released:
  • - 3.2.3_Hotfix |Fix on security for pMode upload |Fix for listPendingMessages 
  • - 3.2.4_Hotfix release fixing the backward compatibility issue detected by ODR
  • In parallel the activities related with the DOMIBUS 3.3 release are ongoing.

SML:

  • SML 3.0.1 release will be concluded with a slight delay of a few days.
  • In parallel the activities for the SML 3.1 release are ongoing, with a slightly slower pace then expected at this point.

SMP:

  • The SMP 3.0 RC2 will be released on the 3rd May, according to with the activityg.

Evolutive Maintenance

Requests for change:


Unable to render Jira issues macro, execution error.  

Unable to render Jira issues macro, execution error.


 

Release calendar:

Mar2016AprMayJunJulAugSepOctNovDecJan2017FebMarAprMayDomibus3.1F-1/35/16Domibus 3.2 RC1 - 15/09/16Domibus 3.3 RC Domibus 3.2 FR - 10/10/16Domibus 3.3 FR - 13/05/17Domibus 3.1.1-3/6/16
eDelivery

Domibus

SML - 15/Jul/16 to 19/Sep/16

SMP - 16/Sep/16 to 03/Feb/17

SMP & AS4 conformance testing service

PKI services set up

Demo Environment

3rd line production support | Patching and bug fixing

PKI service

 

For more details, please consult this page.


 

Milstones progress

Milestone TitleStart DateEnd Date% completeStatus Comments
Domibus 3.2.307/Mar/17

30/Mar/17

100%

COMPLETED


Domibus 3.2.4

14/Mar/17

19/April/17

100%

COMPLETED


Domibus 3.2.5

2/May/17

30/May/17

0%

NOT STARTED


Domibus 3.3 RC111/Oct/1616/Jun/1768%

ONGOING


Domibus 3.3 FR23/Jun/1722/Sep/17

NOT STARTED


Domibus 4.0 RC25/Sep/1716/Mar/18

NOT STARTED

(to be detailed RC1 and FR dates)
Domibus 4.0 FR19/Mar/1818/May/18

NOT STARTED


SML 3.0.116/Sep/1630/Apr/1792%

DELAYED

revised expected completion date 10/May/17
SML 3.118/Nov/1623/Jun/1722%

DELAYED


SML 4.0 RC26/Jun/1730/Mar/18

NOT STARTED


SML 4.0 FR02/Apr/1804/Jun/18

NOT STARTED


SMP 3.0 RC216/Feb/1703/May/1779%

ONGOING


SMP 3.0 FR04/May/1716/Jun/17

NOT STARTED

There is a dependency with the eHealth project for the end date
SMP 4.0 RC19/Jun/1715/Dec/17

NOT STARTED


SMP 4.0 FR18/Dec/1719/Feb/18

NOT STARTED



 

 Operations

Operations management:

Incident Management:


 

Operations management: