703039867OVERALL STATUS:   YELLOW   

Date:   

Reporting Period:   to  


Project Owner (PO): DG CNECT

Business Manager (BM): Maya Madrid

Solution Provider (SP): DIGIT

Project Manager (PM): Bogdan Dumitriu

Section 1: Project Management

Milestones Progress

Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.9

 

 

55%

IN PROGRESS


Domibus 5.1.3

 

 

100%

COMPLETED


Domibus 5.1.4

 

 

100%

COMPLETED


Domibus 5.1.5

 

65%

IN PROGRESS


Domibus 5.2 RC

Q4 2024

68%

IN PROGRESS

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q4 2024

Q4 2024

0%

NOT STARTED

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q1 2025

Q1 2025

0%

NOT STARTED


Domibus 6.0 RC

Q2 2025

Q3 2025

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

Q4 2025

Q4 2025

0%

NOT STARTED


DomiSML 5.0 RC

0%

NOT STARTED


DomiSML 5.0 FR

0%

NOT STARTED

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.1 RC

60%

IN PROGRESS


DomiSMP 5.1 FR

0%

NOT STARTED


eDelivery AS4, SMP, BDXL & ebCore Party Id 2.0 profiles

95%

IN PROGRESS

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

A first public consultation was held between July 2023 - November 2023.

A second public consultation was held between 8 March 2024 - 8 April 2024.

The specifications are to be tentatively adopted in July, after live testing during two events planned in June.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

58%

IN PROGRESS


Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile

52%

ON HOLD


Migration to GITLab

Q4 202412%

ON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Newsroom account for eDelivery (for mailing list management)

?

10%

CANCELLED

The development of a newsroom account for eDelivery has been suspended until the team has full capacity to operate.
Update eDelivery projects & stakeholders repository

50%

IN PROGRESS

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
eDelivery FAQ

 

 

15%

IN PROGRESS

Updating eDelivery knowledge base and display of FAQ in various contexts.
eDelivery Self-Assessment

 

 

20%

IN PROGRESS

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Cost-Analysis tool

5%

IN PROGRESS

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Tutorial slides

 

 

5%

ON HOLD

Review and update to the relating documents to be available on the eDelivery website.
Conformant solutions presentation 

 

100%

COMPLETE

Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. 
Pitch and launch joint Building Blocks social media account

80%

IN PROGRESS

Launch social media accounts together with other Building Blocks.
eDelivery Interoperability Forum 18 April

100%

COMPLETE

 All meeting related activities has been closed.
eDelivery Informal Cooperation Network meeting 15 May

90%

IN PROGRESS

Pending publication of the official minutes and videos to the community.
Interoperability Event 11 & 25 June

35%

IN PROGRESS

 Reminders sent
Webinar on eDelivery value proposition (Member States) 12 December

0%

NOT STARTED


How-to video on Domibus new features 24 October

 

 

0%

NOT STARTED


eDelivery Interoperability Forum 24 October

 

 

0%

NOT STARTED


eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

NOT STARTED


Dynamic Discovery Webinar 26 September

 

 

0%

NOT STARTED


Digital Building Blocks Newsletter No. 5 (June 2024)

70%

IN PROGRESS


eDelivery Newsletter No. 8 (June 2024)

 

 

50%

IN PROGRESS


eDelivery Newsletter No. 9 (September 2024)

 

 

0%

NOT STARTED


eDelivery Newsletter No. 10 (December 2024)

 

 

0%

NOT STARTED


Technical Progress

Specifications: eDelivery AS4, SMP, BDXL, ebCore Party Id 2.0 Profiles

  • Guidance documentation, registration and data collection EU Surveys prepared and shared for the Interoperability Events scheduled for and .
  • Domibus PoC implementing the new specifications prepared for use during the event.
  • PoC validation tool of the new specifications prepared; to be shared with participants.

Software product: Domibus

  • Domibus 5.1.4 bug fix release, including the fixes implemented in 5.0.8, was released on the .
  • Domibus 5.1.5 and 5.0.9 bug/security fix releases are planned for and .
  • Domibus new documentation framework (doc as code)
    • In production, initially with Domibus 5.0.8 release, and now with all the following Domibus versions.

Software product: DomiSMP

  • DomiSMP 5.1 RC development activities are ongoing.

Software product: DomiSML

  • DomiSML 5.0 RC planned to be started on the .

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

  • eDelivery AS4 1.15 profile enhancements conformance testing implementation:
    • Implementation of test cases for the Dynamic Sender profile enhancement ongoing
  • Ongoing support being provided to the SW vendors testing their AS4 solutions.
  • SMP conformance testing: Support and troubleshooting of SW vendor conformance testing activities (Minder platform)
  • Preparations for a bug fix release of the platform is ongoing, it will include the deployment of the PKI path and ENTSOG profile enhancements and several minor bug fixes.

Software product: Docker images

  • N/A

Service: PKI Service

  • N/A

Service: SML Service

  • eDelivery-OpenPeppol discussions and joint work underway for OpenPeppol to move records to a new SML Service it would manage directly.

Onboarding and Communication

Section 2: Evolutive Maintenance

Change Requests

KeySummaryTCreatedUpdatedDueAssigneeReporterPStatusResolution
EDELGOV-89Fulfill the requirements on the BDEW AS4 ProfileOct 28, 2022Sep 22, 2023
Cosmin BACIUSven Uthe

UNDER REVIEW

Unresolved
EDELGOV-76Request for investigation of using multihop functionality with AS4Nov 12, 2020Sep 28, 2022
Marcio SAMPAIOOle Vilstrup Møller


POSTPONED

On hold
EDELGOV-51Dynamic Service discovery - SML/SMP change requestSep 28, 2018Sep 22, 2023
Marcio SAMPAIOCIF VSRS

UNDER REVIEW

Unresolved

Release Calendar

Section 3: Support Office

Incident Management

SMT - workload details

The volume of opened and handled SMT tickets is stable compared to the previous months. In April 2024, there were of questions from users on Docker, Domibus migration, AS4 connectivity test requests, conformance tests, requests to participate in the June 2024 Interoperability forum, feedback from AS4 conformant solutions companies (logos or product names to be updated on the Digital website), etc.

Email interaction

For eDelivery, received mails were related to:

  • Requests for AS4 connectivity test with SHAOKE, Gyptis
  • eDelivery conformance tests: SMP conformance testing on Minder for SierraLima6 Limited ongoing, AS4 conformance testing on GITB platform for Nsoftware
  • Questions from users: request to have the cost and self-assessment tools, Domibus (WS plugin and ‘markAsDownloaded’ attribute, Domibus upgrade from 5.1. to 5.1.1, Docker container image for Domibus 5.1.2, question on certificate and keys), SML/SMP (SMP/SMK certificate update/renewal, question on adding and deleting participants, intermittent lookup issue on SML due to a DNSSEC configuration  error (SNET investigation ongoing)), PKI certificates (CiXP, EUCEG, UDB, EUDAMED, EPREL), TAPAS (ICS2 connectivity test assistance requests (re-directed to the National service desks), onboarding request forwarded to National Helpdesk), followup of issues raised to Oracle support)
  • There was a total of 780 emails in the FMB. We have removed 61 emails for SML Inconsistency, 73 alerts, 14 xmatters and 28 emails from PKI CommisSign from the count, which makes a total of 610 received mails for the reporting month.

PKI

In April 2024, 16 certificates were issued: 2 OOTS, 2 IRI, 4 EUCEG,1 UDB, 4 EUDAMED, 2 CiXP and 1 DECIDE.

Operations Management

SML – availability

The achieved availability for SML1 was within the target for the month of April.

  • No labels