Project progress
The TO team`s processes and procedures were adjusted to ensure business continuity, and with minor disruption we have transitioned to full remote work for mode.
DOMIBUS:.
- 4.1.4 version created to address several detected bugs. This version will be planned if we deem the fixes necessary for our stakeholders before the 4.2 release.
- 4.2 version development activities continue to progress.
eTrustEx adapter replacement Access Point plugin:
- Work on eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC (Multitenacy enabling | minor improvements | bug fixing) is close to conclusion (FR ), however the progress of the test activities as hampered by the remote work that had to be adopted. This may lead to delays in the release date. Assistance of the entities using the adapter with the migration process to the eDelivery Acc Point - eTrustEx Plugin, has also been hampered by the remote work, and by the fact that those entities ceased their activities due to the Corona virus crisis
Evolutive Maintenance
Requests for change:
N/A
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|---|---|---|---|---|
Domibus 4.0.2 | 10/Dec/18 | 11/Feb/19 | 100% | COMPLETED | |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 100% | COMPLETED | Release date and scope redefined follow the anticipation of the 4.1.1 release |
Domibus 4.1.3 | 29/Nov/19 | 10/Feb/20 | 100% | COMPLETED | CXF upgrade (plugin and security issue) |
Domibus 4.1.4 | - | - | - | NOT STARTED | bug fix release not yet planned |
12/Nov/19 | 21/Sep/20 | 31% | ONGOING | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED | |
SML 4.0.1 | 18/Jun/19 | 2/Oct/19 | 100% | COMPLETED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct |
SML 4.0.2 | 29/Nov/19 | 18/Feb/20 | 100% | COMPLETED | code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way. |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 100% | COMPLETED | Bug fix release |
SMP 4.1.1 EC | NOT STARTED | to be planned | |||
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 RC | 30/Jul/18 | 01/Mar/19 | 100% | COMPLETED | |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED | wildfly and mysql |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 | 20/Feb/20 | 100% | COMPLETED | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 31/Mar/20 | 95% | ONGOING | making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations |