Project progress
- Upon the conclusion of Domibus 3.1 FR, there was an increase in the planned activities due to the issues detected (that led to the intermediate release 3.1.1). Moreover the scope of the domibus 3.2 release was changed in order to emphasize the AP robustness and focus on implementing quality control and improvement mechanisms.
- Due to the well documented staffing issue, aggravated by the recent departure of another developer, there was no capacity to tackle the planned activities for the SML and SMP, which were postponed, 1.5 months and 3 months, respectively.
Evolutive Maintenance
Milestones
Summary | Status | Due |
---|---|---|
Support tasks | In Progress | N/A |
SML/BDXL conformance testing services | In Progress | Dec 30, 2016 |
Adoption of JIRA Portfolio as the project planning tool | Closed | Feb 29, 2016 |
SMP Conformance Testing Service | In Progress | Dec 29, 2017 |
AS4 Conformance Testing Service | In Progress | Dec 31, 2016 |
SML 3.0 (SML according to OASIS specs - BDXL) | In Progress | Sep 19, 2016 |
DOMIBUS release 3.3 | Open | Apr 07, 2017 |
DOMIBUS release 3.2 | In Progress | Oct 10, 2016 |
DOMIBUS release 3.1 | Closed | Jun 03, 2016 |
PKI services | In Progress | Dec 30, 2016 |
Demo environment | In Progress | Aug 31, 2016 |
SMP 3.0 | Open | Feb 03, 2017 |
Change Requests
will be discussed at the next OMB with representative of OpenPEPPOL;
AF explained that this would improve the security on plugins; JFR asked if there was an impact on the plugin; AF stated that there was no impact RfC was approved by the OMB;
will be discussed at the next OMB, AF will provide a presentation on the consequences and costs linked to this change.
Operations