703039867OVERALL STATUS: YELLOW
Date:
Reporting Period: toProject Owner (PO): DG CNECT
Business Manager (BM): Maya Madrid
Solution Provider (SP): DIGIT
Project Manager (PM): Bogdan Dumitriu
Section 1: Project Management
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments |
---|---|---|---|---|---|
Domibus 5.0.10 |
| 100% | COMPLETED | ||
Domibus 5.1.7 |
| 100% | COMPLETED | ||
Domibus 5.1.8 |
| TBD | 67% | IN PROGRESS | Release planned for end of April, specific date to be confirmed |
Domibus 5.2 RC | Q3 2025 | 80% | IN PROGRESS | ||
Domibus 5.2 FR | Q3 2025 | Q4 2025 | 0% | NOT STARTED | |
Domibus - technical consolidation / internal tasks | Q4 2025 | Q1 2026 | 0% | NOT STARTED | |
Domibus 6.0 RC | Q1 2026 | Q2 2026 | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward |
Q2 2026 | Q3 2026 | 0% | NOT STARTED | ||
DomiSML 5.0 RC | 90% | IN PROGRESS | |||
DomiSML 5.0 FR | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward | ||
DomiSML 5.0.1 |
|
| 0% | NOT STARTED | |
DomiSMP 5.1.1 |
|
| 0% | NOT STARTED | |
DomiSMP 5.2 RC |
|
| 0% | NOT STARTED | |
DomiSMP 5.2 FR |
|
| 0% | NOT STARTED | |
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 60% | IN PROGRESS | Support for pull enhancement, dynamic sender and dynamic receiver profile enhancements to be introduced in April 2025, but support for Split & Join (the last unsupported profile enhancement) postponed to late 2025. | ||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 52% | ON HOLD | |||
Migration to GITLab | end 2027 | 12% | ON HOLD | The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q4 2025 as use of Atlassian tools (JIRA, BitBucket, Bamboo) currently is extended until February 2026. | |
Update of eDelivery reusing projects & stakeholders repository | | 30% | IN PROGRESS | The milestone will be considered completed when all the eDelivery reusing projects pages are updated and confirmed in Jira with the corresponding project managers. | |
eDelivery FAQ |
|
| 100% | COMPLETED | Published |
eDelivery Self-Assessment |
|
| 95% | IN PROGRESS | Review and update to the relating documents to be available on the eDelivery website. |
Pitch and launch joint Building Blocks social media account | 70% | IN PROGRESS | Launch social media accounts together with other Building Blocks. | ||
Webinar on eDelivery value proposition (Member States) on 3 April |
| 50% | IN PROGRESS | Webinar has been rescheduled for 3 April | |
How-to video on Domibus new features 2024 Q4 |
|
| 0% | NOT STARTED | Rescheduled to Q4 2025. |
eDelivery Interoperability Forum Meeting 27 February |
|
| 100% | COMPLETED | |
Trust Models Webinar on 19 June |
|
| 5% | IN PROGRESS | Webinar has been rescheduled to 19 June 2025 |
12th eDelivery Informal Cooperation Network meeting 7 May 2025 |
|
| 5% | IN PROGRESS | |
eDelivery Newsletter No. 11 (March 2025) |
|
| 100% | COMPLETED | The newsletter No. 11 has been issued on for 1584 recipients |
Digital Building Blocks Newsletter No. 7 (May 2025) |
|
| 15% | IN PROGRESS | |
New conformance testing reports design |
|
| 90% | IN PROGRESS | Updating eDelivery Conformance testing report |
Content review of the website “get started” section |
|
| 30% | IN PROGRESS | |
Cost estimation tool |
|
| 5% | IN PROGRESS | Updating and revamping the cost estimation tool |
eDelivery tutorial |
|
| 30% | IN PROGRESS | Revising the eDelivery tutorial to assist in onboarding stakeholders |
eDelivery Interoperability Event on 16 September 2025 |
|
| 0% | NOT STARTED | |
eDelivery Interoperability Forum Meeting on 16 October 2025 |
|
| 5% | IN PROGRESS | |
eDelivery Newsletter No. 12 (May-June 2025) |
|
| 15% | IN PROGRESS | The content has been identified |
Technical Progress
Specifications: eDelivery AS4, SMP, BDXL, ebCore Party Id Profiles
- The Interoperability post-event report was published on .
- During the Interoperability Forum of 7 service providers indicated they would implement eDelivery 2.0 in 2025 (of which one already did) and 3 in 2026.
Software product: Domibus
- The following patches were released:
- 5.0.10 released on
- 5.1.7 released
- Domibus 5.1.8, which includes fixes to the pull mechanism along with other bug fixes, is planned for release at the end of April.
- Domibus 5.2 RC development work is ongoing
- Due to priority given to patching published released, it has been decided to further postponed the Domibus 5.2 RC to Q3 2025 and FR to Q4 2025.
Software product: DomiSMP
- DomiSMP 5.1.1 activities planned to be started on .
Software product: DomiSML
- DomiSML 5.0 RC development work is ongoing, release planned for the .
- As part of the migration of all eDelivery documentation to a modern "documentation as code" approach, the documentation of DomiSML in the new format was published.
Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service
- The patch release 2023.06-p2 of the platform including several minor bug fixes and a reorganisation of the Specification groups and Specifications hierarchy restructuring was released on .
- eDelivery AS4 1.15 profile enhancements conformance testing implementation:
- Implementation of test cases for the Dynamic Receiver profile enhancement ongoing.
- Standalone tool that will provide limited self-testing/self-validation support to solution providers preparing 2.0-conformant solutions (eDelivery2-AS4-security-validator) will be available by the end of April.
Software product: Docker images
- N/A
Service: PKI Service
- N/A
Service: SML Service
- N/A
Section 2: Evolutive Maintenance
Change Requests
Key | Summary | T | Created | Updated | Status | Resolution |
---|---|---|---|---|---|---|
EDELGOV-132 | JMX Authentication support | Feb 18, 2025 | Mar 24, 2025 | APPROVED | Unresolved | |
EDELGOV-116 | Domibus features - iSupport | Nov 04, 2024 | Mar 24, 2025 | APPROVED | Unresolved | |
EDELGOV-89 | Fulfill the requirements on the BDEW AS4 Profile | Oct 28, 2022 | Feb 11, 2025 | UNDER REVIEW | Unresolved | |
EDELGOV-76 | Request for investigation of using multihop functionality with AS4 | Nov 12, 2020 | Sep 28, 2022 | POSTPONED | On hold | |
EDELGOV-51 | Dynamic Service discovery - SML/SMP change request | Sep 28, 2018 | Feb 11, 2025 | UNDER REVIEW | Unresolved |
Release Calendar
Section 3: Support Office
Incident Management
SMT - workload details
The number of handled, opened and resolved SNOW tickets is stable since few month. The increase of SNOW tickets starting in July 2024 can be explained mainly because of eDelivery PKI Certificates that are expiring and need to be issued. Questions from users are questions on Docker, Domibus migration (database migration issues and others), plugins, conformance and connectivity tests requests and questions, questions on Domibus/DomiSMP etc.
Email interaction
For eDelivery, received mails were related to:
In January 2025, received mails were related to:
- eDelivery AS4 connectivity test: Euro Information, Appfuxion Consulting Sdn. Bhd, Samer & Co. Shipping
- eDelivery conformance tests: new version of Harmony, Tigron (SMP and AS4 conformance testing), Axway 1.15, Eufex Deutschland GmbH request for AS4 conformance test (product is eConnect Europe)
- Peppol test onboarding procedure – test completed, gaps and documentation ongoing
- Invitation to Feature Domibus, DomiSMP, DomiSML in the DSSC Toolbox (Data Spaces Support Centre)
- Questions from users: eDelivery assessment tool availability, Domibus (support of Java Oracle JDK 21 and Apache Tomcat 10.1, question on pentest for Domibus 5.1.6, on multitenancy, Domibus on Docker, etc.), SML/SMP (SMP/SMK certificate update/renewal, participant registration, question on add/delete service group in SMP), PKI certificates (DIGG, UDB, CiXP, EPREL, PCN, BRIS, EUDAMED, ECDB), TAPAS (ICS2 connectivity test assistance requests, issue with Oracle partitioning and Domibus 5.1.5, meeting on push/pull mode, performance test scenarios and forecast for 2025 from the teams, etc.)
- There was a total of 852 emails in the FMB. We have removed 92 emails for SML Inconsistency, 68 alerts, and 150 emails from PKI CommisSign from the count, which makes a total of 542 received mails for the reporting month.
In February 2025, received mails were related to:
- eDelivery AS4 connectivity test: Stratum, Euro Information, BEO, Appfuxion Consulting Sdn. Bhd, Samer & Co. Shipping
- eDelivery conformance tests: deployment of patch 2 by SO/TO, Opentunnel resumed conformance tests after patch 2 release, IPWorks EDI (testing of ENTSOG and additional profile enhancements), new version of Harmony, Axway 1.15, Eufex Deutschland GmbH request for AS4 conformance test resumed conformance testing with patch 2 release (product is eConnect Europe)
- Questions from users: Domibus (alerts configuration in Domibus, using Domibus to meet ETSI requirements on ERDS, Docker, issue with Oracle after upgrade to Domibus 5.1.7 (Domibus generates exceptions), MySQL db and CPU usage, post messages with REST API, etc.), SML/SMP (SMP/SMK certificate update/renewal, participant registration), PKI certificates (UDB, CiXP, IRI, EPREL, PCN, BRIS, EUDAMED, ECDB), TAPAS (ICS2 connectivity test assistance requests, purging of messages, CXF library upgrade included in the latest patch 5.0.8-PATCH-EA-PULL-CXF, etc.)
- There was a total of 596 emails in the FMB. We have removed 84 emails for SML Inconsistency, 10 alerts, and 47 emails from PKI CommisSign from the count, which makes a total of 455 received mails for the reporting month.
PKI
In January 2025, 43 PKI certificates were Issued: 5 SE-DIGG, 1 TACHONET, 1OOTS, 4 PCN, 9 ECDB, 13 CiXP, 3 EUDAMED, 1 BRIS and 7 EPREL.
In February 2025, 15 PKI certificates were issued: 1 OOTS, 2 DECIDE, 1 PCN, 1 ECDB, 3 CiXP, 5 EUDAMEDand 2 EPREL.
Operations Management
SML – availability
The achieved availability for SML was within the target for the months of January and February.