703039867OVERALL STATUS: YELLOW
Date:
Reporting Period: toProject Owner (PO): DG CNECT
Business Manager (BM): Maya Madrid
Solution Provider (SP): DIGIT
Project Manager (PM): Bogdan Dumitriu
Section 1: Project Management
Milestones Progress
Title | Start Date | End Date | % completed | Status | Comments |
---|---|---|---|---|---|
Domibus 5.0.8 | TBD | 93% | IN PROGRESS | Bug fix release. Despite its substantial scope, due to the non criticality of the bug fixes included in this release and the team limited capacity it was decided to put this release on hold for the moment | |
Domibus 5.1.2 | 100% | COMPLETED | bug and security fix release | ||
Domibus 5.2 RC | End Q1 2024 (uncertain, may change) | 66% | IN PROGRESS | Release date postponed from the , following the roadmap review | |
Domibus 5.2 FR | Q2 2024 | Q2 2024 (uncertain, may change) | 0% | NOT STARTED | Release date postponed from the , following the roadmap review |
Domibus - technical consolidation / internal tasks | Q2 2024 | Q3 2024 | 0% | NOT STARTED | |
Domibus 6.0 RC | Q3 2024 | 2025 | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward |
Domibus 6.0 FR | 2025 | 2025 | 0% | NOT STARTED | |
DomiSML 5.0 RC | 0% | NOT STARTED | |||
DomiSML 5.0 FR | 0% | NOT STARTED | Dependent on budget confirmation as of May 2025 onward | ||
DomiSMP 5.1 RC | 60% | IN PROGRESS | |||
DomiSMP 5.1 FR | 0% | NOT STARTED | |||
eDelivery AS4 2.0 profile | 85% | IN PROGRESS | The main focus of this profile version is the upgrade to new cryptographic algorithms. Public consultation held between July 2023 - November 2023. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. A second draft of the specifications is almost ready and a new public consultation will be necessary. The milestone and progress were updated to reflect this. | ||
eDelivery SMP 2.0 profile | 85% | IN PROGRESS | The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0. Public consultation started in June. Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication. A second draft of the specifications is almost ready and a new public consultation will be necessary. The milestone and progress were updated to reflect this. | ||
Conformance testing service: Full support for eDelivery AS4 1.15 profile | 50% | IN PROGRESS | |||
Conformance testing service: Extended coverage of eDelivery AS4 1.15 Common Profile | 52% | IN PROGRESS | |||
Migration to GITLab | Q4 2024 | 12% | ON HOLD | The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024. | |
Define and implement a new documentation model for the eDelivery sample implementations | Q1 2024 | 95% | IN PROGRESS | Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer. Updated completion date to Q1 2024 following the re-planning. | |
Newsroom account for eDelivery (for mailing list management) | ? | 10% | CANCELLED | The development of a newsroom account for eDelivery has been suspended. | |
Update eDelivery projects & stakeholders repository | 40% | IN PROGRESS | The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers. | ||
Overhaul of eDelivery communication materials | 50% | CANCELLED | This Milestone has been broken down into the remaining specific communications materials for 2024. | ||
Increase average online engagement rate to 15% | 30% | CANCELLED | The eDelivery X account will transition to a joint Building Blocks account. | ||
Ninth meeting of the Informal Cooperation Network for eDelivery (ICN), November 2023 | 100% | COMPLETE | |||
eDelivery Interoperability Forum 28 November 2023 | 100% | COMPLETE | |||
eDelivery FAQ (overhaul of communication materials) |
|
| 15% | IN PROGRESS | Updating eDelivery knowledge base and display of FAQ in various contexts. |
eDelivery Self-Assessment and Cost-Analysis tools (overhaul of communication materials) |
|
| 5% | IN PROGRESS | Review and update to the relating documents to be available on the eDelivery website. |
eDelivery Tutorial materials (overhaul of communication materials) | Tbc. |
| 0% | NOT STARTED | |
Conformant solutions presentation |
|
| 60% | IN PROGRESS | Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. |
Pitch and launch joint Building Blocks social media account |
| 20% | IN PROGRESS | Launch social media accounts together with other Building Blocks. | |
eDelivery Interoperability Forum 29 February |
|
| 30% | IN PROGRESS | |
How-to video on DomiSMP 5.0 new features published |
|
| 20% | IN PROGRESS | |
eDelivery Interoperability Forum 18 April |
|
| 5% | IN PROGRESS | |
eDelivery Informal Cooperation Network meeting 15 May |
|
| 5% | IN PROGRESS | |
Interoperability Event 11 June |
|
| 0% | NOT STARTED | |
Webinar on eDelivery value proposition (Member States) 26 September |
|
| 0% | NOT STARTED | |
How-to video on Domibus new features 24 October |
|
| 0% | NOT STARTED | |
eDelivery Interoperability Forum 24 October |
|
| 0% | NOT STARTED | |
eDelivery Informal Cooperation Network meeting 19 November |
|
| 0% | NOT STARTED | |
Dynamic Discovery Webinar 12 December |
|
| 0% | NOT STARTED | |
eDelivery Newsletter No. 7 (March 2024) |
|
| 0% | NOT STARTED | |
eDelivery Newsletter No. 8 (June 2024) |
|
| 0% | NOT STARTED | |
eDelivery Newsletter No. 9 (September 2024) |
|
| 0% | NOT STARTED | |
eDelivery Newsletter No. 10 (December 2024) |
|
| 0% | NOT STARTED |
Overall Project Progress
Technical
- The second drafts of the eDelivery AS4 2.0 and eDelivery SMP 2.0 profile are almost complete. A new version of the eDelivery BDXL (v2.0) will also be proposed as part of the changes (under preparation).
- The disposition of public review comments and the new versions will be finalised shortly.
- Domibus 5.1.2 bug fix release was published on the
- Domibus 5.0.8 bug fix release is postponed due to capacity issues.
- Limited progress on Domibus 5.2 due to extensive maintenance and support workload. Further delays in its release date are likely.
- DomiSMP 5.1 RC development activities are ongoing.
- eDelivery Conformance Testing service: Implementation of test cases for the Dynamic Sender profile enhancement ongoing. Analysis to strengthen the testing of the eDelivery Common Profile concluded. Work also ongoing to increase the level of service maturity.
- A new document, “Architecture, Infrastructure, Operations and Maintenance of an SML Service” was finalised and published in order to facilitate the creation by others of services similar to the SML service.
Onboarding & Communication
- Three new digital ecosystems using eDelivery went live:
- Central Electronic System of Payment information (CESOP) provides tax administration of the EU Member States with payment information allowing them to detect VAT fraud more easily.
- Union Biofuels Database (UDB) serves as a central database for public or private fuel supply-chain actors that provides a clear oversight on the supply chain of biofuels.
- Once Only Technical System simplifying cross-border online procedures by allowing citizens and businesses to supply the same data to public authorities ‘only once’.
- eDelivery newsletter circulated on 14 December was sent to 1440 readers and reached an opening rate of 103% due to forwarding. Read the online version
- eDelivery events planned for 2024
- A second consultation for the updated eDelivery AS4 2.0 and SMP 2.0 standards is coming soon.
Technical Progress
Specifications: eDelivery AS4 & SMP Profiles
- Following feedback received for the consultation, the specifications are being modified in non-trivial ways:
- The second drafts of the eDelivery AS4 2.0 and eDelivery SMP 2.0 profile are almost complete. A new version of the eDelivery BDXL (v2.0) will also be proposed as part of the changes (under preparation).
- The disposition of public review comments and the new versions will be finalised shortly.
- The OMB is formally asked to approve the launch of the second public consultation for the revised draft specifications.
- The second drafts of the eDelivery AS4 2.0 and eDelivery SMP 2.0 profile are almost complete. A new version of the eDelivery BDXL (v2.0) will also be proposed as part of the changes (under preparation).
Software product: Domibus
- Domibus 5.1.2 bug fix release was published on the
- Domibus 5.0.8 bug fix release
- The release of this version is currently on hold. Despite its substantial scope, the non criticality of the bugs addressed in this version and the limited capacity of the TO it was decided not to proceed or plan the release of this version for the moment.
- Domibus 5.2 RC
Limited progress due to the effort required for 5.1.2 and the extensive maintenance and support workload. Leaving limited capacity for development tasks, as highlighted in the issue EDELIVERY-11247. Due to the prolonged onset of this dynamic, it is highly likely that it will lead to further delays in its release dates.
- Following the publication of secure deployment guidelines, users of Domibus were informed that as of emergency security patches will only be released to address vulerabilities that are exploitable in installations that follow the guidelines.
Software product: DomiSMP
- DomiSMP 5.1 RC development activities are ongoing.
Software product: DomiSML
- DomiSML 4.3 Vulnerability Assessment Report received and analyzed. No major issues detected. Feedback provided to the security team. New version of the report is expected.
Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service
- eDelivery AS4 1.15 profile enhancements conformance testing implementation:
- Limited progress due to the extended absence of the team member responsible for this activity
- Implementation of test cases for the Pull profile enhancement on hold, due to the need for analysis work in some specific test cases
- Implementation of test cases for the Dynamic Sender profile enhancement ongoing
- Analysis to strengthen the testing of the eDelivery Common Profile (the mandatory part of the profile that is implemented by all conformant products) concluded.
- Work with SMCO and SO for new presentation of conformant solutions and formalising the release process of the eDelivery Conformance Testing Service (to increase level of service maturity)
Software product: Docker images
- Domibus 5.1.2 in a Tomcat + MySQL configuration Docker images for published on the (OOTS).
- Docker image performance testing activities are ongoing.
Service: PKI Service
- N/A
Service: SML Service
- A new document, “Architecture, Infrastructure, Operations and Maintenance of an SML Service” was finalised and published in order to facilitate the creation by others of services similar to the SML service.
Section 2: Evolutive Maintenance
Change Requests
Key | Summary | T | Created | Updated | Due | Assignee | Reporter | P | Status | Resolution |
---|---|---|---|---|---|---|---|---|---|---|
EDELGOV-110 | DOMIBUS - Support of HSM ( hardware devices) | Dec 26, 2023 | Feb 6, 2024 | Cosmin BACIU | Gregory STEENBEEK | REJECTED | Rejected | |||
EDELGOV-109 | DOMIBUS to support security hardware | Dec 21, 2023 | Feb 6, 2024 | Cosmin BACIU | Gregory STEENBEEK | REJECTED | Rejected | |||
EDELGOV-108 | Support Prometheus compatible metrics | Dec 12, 2023 | Feb 6, 2024 | Cosmin BACIU | Gregory STEENBEEK | REJECTED | Rejected | |||
EDELGOV-107 | Provide scripts for scheduled automated updates of PModes or Trust Stores | Nov 15, 2023 | Feb 6, 2024 | Cosmin BACIU | Pim VAN DER EIJK | REJECTED | Rejected | |||
EDELGOV-92 | eDelivery growth factor by improved DNS recommendation of SML discovery | Dec 2, 2022 | Oct 23, 2023 | Joze RIHTARSIC | Gunnar Nilsson | UNDER REVIEW | Unresolved | |||
EDELGOV-89 | Fulfill the requirements on the BDEW AS4 Profile | Oct 28, 2022 | Sep 22, 2023 | Cosmin BACIU | Sven Uthe | UNDER REVIEW | Unresolved | |||
EDELGOV-76 | Request for investigation of using multihop functionality with AS4 | Nov 12, 2020 | Sep 28, 2022 | Marcio SAMPAIO | Ole Vilstrup Møller | POSTPONED | On hold | |||
EDELGOV-51 | Dynamic Service discovery - SML/SMP change request | Sep 28, 2018 | Sep 22, 2023 | Marcio SAMPAIO | CIF VSRS | UNDER REVIEW | Unresolved |
Release Calendar
Section 3: Support Office
Incident Management
SMT - Workload Details
The volume of tickets and Jira issues remained quite stable in October 2023, compared to the previous months. Requests from users concern usual questions on Domibus and the different plugins, Domibus migration and migration scripts, AS4 connectivity test issues, conformance tests questions and issues, Domibus and Docker, etc.
Email Interaction
For eDelivery, received emails were related to:
- Requests for AS4 connectivity test with RIMS
- eDelivery conformance tests- questions from Opentext that is running the tests with the new GITB platform
- PKI SOD for OOTS project finalised and sent
- Request to use eDelivery SML services from a company working for the Polish Ministry of Digital Affairs – SML subdomain request form sent to customer - ongoing
- Questions from users: Domibus (usage of plugins and plugin users, Domibus migration scripts to Domibus 5.0 and 5.1, compatibility with ActiveMQ Artemis, issue with Domibus start in Docker container, question on WS backend plugin), updated list of Peppol participants provided, SML/SMP (SMP/SMK certificate update/renewal,), PKI certificates (UDB, EPREL, BRIS, EUDAMED), TAPAS (Domibus 5.1.1 release and access to the Digital site only for TAPAS users, ICS2 connectivity test assistance requests (re-directed to the National service desks), onboarding request forwarded to National Helpdesk))
- There was a total of 639 emails in the FMB. We have removed 66 emails for SML Inconsistency, 14 xmatters and 5 emails from PKI CommisSign from the count, which makes a total of 554 received mails for the reporting month.
PKI
In October 2023, 3 certificates were issued: 1 for DECIDE, 1 for EPREL and one for EUDAMED.
Operations Management
SML – Availability
The achieved availability for SML1 was within the target for the month of October.