Title

Start Date

End Date

% completed

Status

Comments

Domibus 5.0.8

TBD

93%

Status
colourYellow
titlein progress

Bug fix release. Despite its substantial scope, due to the non criticality of the bug fixes included in this release and the team limited capacity it was decided to put this release on hold for the moment

Domibus 5.1.2

100%

Status
colourGreen
titlecompleted

bug and security fix release

Domibus 5.2 RC

End Q1 2024 (uncertain, may change)

66%

Status
colourYellow
titlein progress

Release date postponed from the , following the roadmap review

Domibus 5.2 FR

Q2 2024

Q2 2024 (uncertain, may change)

0%

Status
colourGrey
titlenot started

Release date postponed from the , following the roadmap review

Domibus - technical consolidation / internal tasks

Q2 2024

Q3 2024

0%

Status
colourGrey
titlenot started


Domibus 6.0 RC

Q3 2024

2025

0%

Status
colourGrey
titlenot started

Dependent on budget confirmation as of May 2025 onward

Domibus 6.0 FR

2025

2025

0%

Status
colourGrey
titlenot started


DomiSML 5.0 RC

0%

Status
colourGrey
titlenot started


DomiSML 5.0 FR

0%

Status
colourGrey
titlenot started

Dependent on budget confirmation as of May 2025 onward

DomiSMP 5.1 RC

60%

Status
colourYellow
titlein progress


DomiSMP 5.1 FR

0%

Status
colourGrey
titlenot started


eDelivery AS4 2.0 profile 

85%

Status
colourYellow
titlein progress

The main focus of this profile version is the upgrade to new cryptographic algorithms.

Public consultation held between July 2023 - November 2023.

Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.

A second draft of the specifications is almost ready and a new public consultation will be necessary. The milestone and progress were updated to reflect this.

eDelivery SMP 2.0 profile

85%

Status
colourYellow
titlein progress

The main focus of this profile version is the upgrade to new cryptographic algorithms and support SMP 2.0.

Public consultation started in June.

Milestone updated to reflect the full profile approval lifecycle, including public consultation and publication.

A second draft of the specifications is almost ready and a new public consultation will be necessary. The milestone and progress were updated to reflect this.

Conformance testing service: Full support for eDelivery AS4 1.15 profile

50%

Status
colourYellow
titlein progress


Conformance testing service:  Extended coverage of eDelivery AS4 1.15 Common Profile

52%

Status
colourYellow
titlein progress


Migration to GITLab

Q4 202412%

Status
colourBlue
titleON HOLD

The preliminary exercise of duplicating the DomiSMP and Domibus project in GITLab for viability test purposes concluded. Activity on hold until Q1 2024.
Define and implement a new documentation model for the eDelivery sample implementations

Q1 2024

95%

Status
colourYellow
titlein progress

Due to the absence of capacity of the TO, the activities have been progressing sluggishly due to the limited support provided to the Technical writer.

Updated completion date to Q1 2024 following the re-planning.


Newsroom account for eDelivery (for mailing list management)

?

10%

Status
titleCANCELLED

The development of a newsroom account for eDelivery has been suspended.
Update eDelivery projects & stakeholders repository

40%

Status
colourYellow
titlein progress

The milestone will be considered completed when all the project pages are updated and confirmed with the corresponding project managers.
Overhaul of eDelivery communication materials

50%

Status
colourRed
titlecancelled

This Milestone has been broken down into the remaining specific communications materials for 2024.
Increase average online engagement rate to 15%

30%

Status
colourRed
titlecancelled

The eDelivery X account will transition to a joint Building Blocks account.

Ninth meeting of the Informal Cooperation Network for eDelivery (ICN), November 2023

100%

Status
colourGreen
titleComplete


eDelivery Interoperability Forum 28 November 2023

100%

Status
colourGreen
titleComplete


eDelivery FAQ (overhaul of communication materials)

 

 

15%

Status
colourYellow
titlein progress

Updating eDelivery knowledge base and display of FAQ in various contexts.
eDelivery Self-Assessment and Cost-Analysis tools (overhaul of communication materials)

 

 

5%

Status
colourYellow
titlein progress

Review and update to the relating documents to be available on the eDelivery website.
eDelivery Tutorial materials (overhaul of communication materials)

Tbc.

 

0%

Status
colourGrey
titlenot started


Conformant solutions presentation 

 

 

60%

Status
colourYellow
titlein progress

Solutions that passed the conformance testing for eDelivery will be displayed on the eDelivery website, including their conformance certificate. 
Pitch and launch joint Building Blocks social media account

  

20%

Status
colourYellow
titlein progress

Launch social media accounts together with other Building Blocks.
eDelivery Interoperability Forum 29 February 

 

 

30%

Status
colourYellow
titlein progress

 
How-to video on DomiSMP 5.0 new features published

 

 

20%

Status
colourYellow
titlein progress

 
eDelivery Interoperability Forum 18 April 

 

 

5%

Status
colourYellow
titlein progress

 
eDelivery Informal Cooperation Network meeting 15 May

 

 

5%

Status
colourYellow
titlein progress

 
Interoperability Event 11 June

 

 

0%

Status
colourGrey
titlenot started

 
Webinar on eDelivery value proposition (Member States)  26 September

 

 

0%

Status
colourGrey
titlenot started

 
How-to video on Domibus new features 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Interoperability Forum 24 October

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Informal Cooperation Network meeting 19 November

 

 

0%

Status
colourGrey
titlenot started

 
Dynamic Discovery Webinar 12 December

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 7 (March 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 8 (June 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 9 (September 2024)

 

 

0%

Status
colourGrey
titlenot started

 
eDelivery Newsletter No. 10 (December 2024)

 

 

0%

Status
colourGrey
titlenot started

 

Overall Project Progress

Technical

...

  • Following feedback received for the consultation, the specifications are being modified in non-trivial ways:
    • The second drafts of the eDelivery AS4 2.0 and eDelivery SMP 2.0 profile are almost complete. A new version of the eDelivery BDXL (v2.0) will also be proposed as part of the changes (under preparation).
    • The disposition of public review comments and the new versions will be finalised shortly.
    • The OMB is formally asked to approve approved the launch of the second public consultation for the revised draft specifications.

Software product: Domibus

...

  • DomiSML 4.3 Vulnerability Assessment Report received and analyzed. No major issues detected. Feedback provided to the security team. New version of the report is expected.

Software product: eDelivery Conformance Testing Platform / Service: Conformance Testing Service

...