Project progress
DOMIBUS:.
- A version 4.1.4 was released on the exclusively to the OpenPEPPOL community, in accordance with the existing Building Blocks cyber security procedures, since this vulnerability only affected this particular project.
- 4.1.5 version, a patch release with several security updates, was released on the 3rd September.
- 4.2
- RC version was released on the 21st September as planned
SML:
- The SML release, 4.0.3, ( planned for (FR) - Security features and updates | Upgrade libraries to latest possible versions and fix OWASP threats) activities are progressing at good pace.
Rest API:
- Alignment of APIs4IPS meeting with JRC held on the
- Scoping document activities ongoing
Blockchain
Discussion ongoing regarding the implementation of blockchain - time stamping and stats. Assistance requirements from the eDelivery DEV team to the process is being prepared- Development concluded and testing phase foreseen to start on the 1st Oct.
HTML |
---|
<div class="banner--top-border"></div> |
Evolutive Maintenance
Requests for change::
Risks and Issue management:
Risks:
Clé | Résumé | T | Création | Mise à jour | Echéance | Attribution | Rapporteur | Pr | Etat | Résolution |
---|---|---|---|---|---|---|---|---|---|---|
EDELIVERY-6762 | Security issues handling process for all the BB | DIGIT S | juin 19, 2020 | janv. 27, 2021 | Marcio SAMPAIO | Marcio SAMPAIO | IN PROGRESS | Unresolved | |||
EDELIVERY-6397 | Domibus 4.2 release | Capacity issues | mars 03, 2020 | janv. 06, 2021 | Bogdan DUMITRIU | Marcio SAMPAIO | CLOSED | Fixed | |||
EDELIVERY-4634 | eDelivery AS4 profile version 1.15 approval delays | mai 14, 2019 | janv. 22, 2021 | Marcio SAMPAIO | Marcio SAMPAIO | CLOSED | Fixed |
Issues:
Clé | Résumé | T | Création | Mise à jour | Echéance | Attribution | Rapporteur | Pr | Etat | Résolution |
---|---|---|---|---|---|---|---|---|---|---|
EDELIVERY-7774 | Uncertainty regarding the value of DEP budget impacts eDelivery roadmap | janv. 26, 2021 | janv. 26, 2021 | Marcio SAMPAIO | Marcio SAMPAIO | OPEN | Unresolved |
Milestones progress:
Milestone Title | Start Date | End Date | % complete | Status | Comments |
---|
eDelivery Access Point - e-TrustEx Backend Plugin version 1.1 FR | 04/Mar/19 | 30/Apr/19 | 100% | COMPLETED |
wildfly and mysql | |||||
01/Jun/21 | 01/Jul/21 | - | NOT STARTED | Use EU Login for SMP console | Upgrade libraries to lastes possible versions and fix OWASP threats | Security features and updates | |
SML 4.0.3 | 20/Oct/20 | 10/Nov/20 | 76% | ONGOING | Security features and updates | Upgrade libraries to lastes possible versions and fix OWASP threats |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 FR | 20/Feb/20 | 8/Jun/2020 |
100% | COMPLETED | Release date |
: 8th June Release delayed from the |
31st March to |
the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations | |||||
Domibus 4.1 FR | 21/Mar/19 | 31/Jul/19 | 100% | COMPLETED | Release date postponed from the 24th May to 15th July | Release date postponed from the 15th July to the 31st July |
Domibus 4.1 RC | 24/Sep/18 | 20/May/19 | 100% | COMPLETED | Release date postponed from the 1st March to 20th May |
Domibus 4.1.1 | 01/Aug/19 | 16/Sept/19 | 100% | COMPLETED | Release date anticipated from 11th Nov to 16th Sept |
Domibus 4.1.2 | 17/Sep/19 | 29/Nov/19 | 100% | COMPLETED | Release date and scope redefined follow the anticipation of the 4.1.1 release |
100%
COMPLETED
CXF upgrade (plugin and security issue)
NOT STARTED
NOT STARTED
SML 4.0 RC | 26/Nov/18 | 15/May/19 | 100% | COMPLETED | Postponed from the 21st Jan to the 15 May as agreed in a previous OMB |
eDelivery Access Point - e-TrustEx Backend Plugin version 1.2 RC | 03/May/19 |
20/ |
Feb/ |
20 | 100% | COMPLETED |
COMPLETED
making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations | |||||
Domibus 4.1.3 | 29/Nov/19 | 10/Feb/20 | 100% | COMPLETED | CXF upgrade (plugin and security issue) |
SML 4.0.2 | 29/Nov/19 | 18/Feb/20 | 100% | COMPLETED | code freeze 6th Jan | release in acc 31st Jan | Prod release 18th | new service for support team that they can update or delete large SMP data in controlled way. |
SML 4.0. |
1 |
18/ |
Jun/ |
19 |
2/ |
Oct/ |
19 |
100% |
ONGOING
COMPLETED | bug fix release | Testing from the 2nd Aug | Release in ACC 4th Sept | Prod postponed from 18th Sept to 2nd Oct | ||||
Domibus 4.1.4 | - | - | - | NOT STARTED | bug fix release not yet planned |
SMP 4.1.1 | 16/May/19 | 10/Oct/19 | 100% | COMPLETED | Bug fix release |
Domibus 4.0.2 |
10/ |
Dec/ |
18 |
11/ |
Feb/ |
19 |
COMPLETED
COMPLETED
COMPLETED
100% |
NOT STARTED
COMPLETED | |||||
12/Nov/19 | 21/Sep/20 | 70% | ONGOING | ||
Domibus 4.2 FR | 22/Sep/20 | 10/Dec/20 | - | NOT STARTED | |
SML 4.0 FR | 16/May/19 | 17/Jun/19 | 100% | COMPLETED |
eDelivery Access Point - e-TrustEx Backend Plugin version 1. |
1 RC |
30/ |
Jul/ |
18 |
01/ |
Mar/ |
19 | 100% | COMPLETED |
Release date: 8th June
Release delayed from the 31st March to the 22nd May do to the need to support the SO office in upgrading the plugin environments in the EC
making the plugins work in Domibus multi-tenant | security enhancement in interactions to backend | minor bugs fixes Operations