For the project objectives:

The report should provide an overview of the project objectives for the reporting period in question, as included in Annex I of the Grant Agreement. These objectives are required so that this report is a stand-alone document.
Please include a summary of the recommendations from the previous reviews (if any) and indicate how these have been taken into account.

For the project progress:

The report should provide a concise overview of the progress of the work in line with the structure of Annex I of the Grant Agreement.

For each work package - please provide the following information:

Note: This should not include project management information. This should be reported in section 3.5.

  • A summary of progress towards objectives and details for each task;
  • Highlight clearly significant results;
  • If applicable, explain the reasons for deviations from Annex I and their impact on other tasks as well as on available resources and planning;
  • If applicable, explain the reasons for failing to achieve critical objectives and/or not being on schedule and explain the impact on other tasks as well as on available resources and planning (the explanations should be coherent with the declaration by the project coordinator) ;
  • a statement on the use of resources, in particular highlighting and explaining deviations between actual and planned man-months per work package and per beneficiary in Annex 1 (Description of Work)
  • If applicable, propose corrective actions.
     

Deliverables and milestones table:

Deliverables (excluding the periodic and final reports)
        
Please list all the deliverables due in this reporting period, as indicated in Annex I of the Grant Agreement.
Deliverables that are of a nature other than written "reports", such as "prototypes", "demonstrators" or "others", should also be accompanied by a short report, so that the European Commission has a record of their existence.
If a deliverable has been cancelled or regrouped with another one, please indicate this in the column "Comments".
If a new deliverable is proposed, please indicate this in the column "Comments".
This table is "cumulative", that is, it should always show all deliverables from the beginning of the project.
                                                                                                                                                                                                                

Table 1. Deliverables[1]

Del. no.

Deliverable name

WP no.

Lead participant

Nature

Dissemination
level


Due delivery date from Annex I

Delivered
Yes/No

Actual / Forecast delivery date

Comments

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  
 

Milestones
Please complete this table if milestones are specified in Annex I of the Grant Agreement.
Milestones will be assessed against specific criteria and performance indicators as defined in Annex I.
  

Table 2. Milestones

Milestone
no.

Milestone name

Due achievement date from Annex I

Achieved
Yes/No

Actual / Forecast achievement date

Comments

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 