1. Introduction
1.1 Legal Background and Status of the Guidelines
(i) Humanitarian Aid Regulation, 1996
(ii) The Financial Regulation and the Implementing Rules
(iii) Framework Partnership Agreements
(iv) Other Reference Documents
1.2 Structure of the Guidelines
1.3 Scope and Applicability of the Guidelines
Table 1 - When Do the Guidelines apply?
(i) Employment contracts vs. Service Contracts
(ii) Implementing Partners vs. Contractors
Table 2: Distinction between Contractors and Implementing Partners2. Mandatory Principles
2.1 Scope and legal basis of the Mandatory Principles
2.2 The Principle of Ethical Procurement
(i) Ethical behaviour of the Contracting Authority
Avoidance of Conflict of Interests
Gifts and gratuities
Table 3 – Good Practice concerning the receipt of gifts and avoidance of
conflicts of interests
Regularity of procurement procedures
Due Diligence and Risk Management
(ii) Ethical behaviour of contractors
2.3 The Principle of Transparency in the Procurement process
(i) Transparency and Open Competition
(ii) Exclusion Criteria
(iii) Selection Criteria
(iv) Award Criteria and Best Value for Money
(v) Respect of confidentiality
(vi) Right of access for the purposes of verifications and audits
2.4 The Principle of Proportionality between the procedures followed for awarding contracts and the value of the contracts
2.5 The Principle of Equal treatment and non-discrimination of potential contractors and donors
(i) Equal Treatment of Candidates and Tenderers
(ii) Equal Treatment of Donors3. General Rules and Procedures
3.1 Scope of the Guidelines on the General Rules and Procedures
3.2 Guidance on procedures for the award of all procurement contracts (including those below €60.000)
(i) The main elements of a contract
Subject
Value
Lots
Duration
(ii) Different parts of the contract document
Incoterms
Transport & Insurance
Force Majeure
(iii) Procurement for awards under €60 000
3.3 Rules for the award of contracts of an amount higher than €60.000 (obligatory for "A" Control mechanism contracts above €60.000)
(i) The different Procurement procedures
(ii) Different kinds of procurement
Table 4 - Procurement in Contracts over € 60.000
(iii) The Negotiated Procedure
Table 5 - Overview of the Negotiated Procedure
(iv) Negotiated procedure with a single tender ("Single Bid Negotiated
Procedure")
(v) Open Tender Procedure
Table 6 - Overview of the Open Tender Procedure
Table 7 - Overview of the different procurement procedures4. Special Rules
4.1 Scope of the Special Rules
4.2 Urgent Actions
4.3 Specific requirements for the procurement of pharmaceutical products and medical devices
(i) Pre-Qualification of pharmaceutical products and medical devices
(ii) Particular selection criteria for pharmaceuticals and medical devices
(iii) The procurement procedures for pharmaceuticals and medical devices
Identification of Pre-Qualified Candidates
Invitation to Pre-Qualified Candidates to Negotiate
Table 8 - Overview of the Negotiated Procedure based on Pre-Qualification
4.4 Food aid procurement rules and procedures
(i) Particular selection criteria for food products
(ii) Monitoring Agencies
Obligations related to the use of a Monitoring Agency
4.5 Pre-established stocks
(i) Eligible Costs when using pre-established stock
(ii) Stockpiling as an activity in the Action
4.6 Framework contracts
(i) Multiple framework contracts
(ii) Procurement procedure for Framework Contracts
(iii) Award of specific contracts based on Framework contracts
Reopening of competition on the basis of a multiple framework contract
Advantages and limitations of Framework contracts
Table 9 – Use of Framework Contracts
4.7 Humanitarian Procurement Centres
(i) Characteristics of Humanitarian Procurement Centres
Definition & Legal Personality
What HPCs supply
– Procurement entities which cannot be recognised as HPCs
Table 10 - Overview of supply chain management options
(ii) The relationship between DG ECHO and HPCs
On what basis does DG ECHO recognise an HPC?
Desk-Reviews and On-site Examinations
Fair pricing system & non-profit principle
Observance of the HPC Charter
When can DG ECHO terminate HPC Recognition?
(iii) The relationship between Partners and HPCs
What are the advantages for a Partner in dealing with an HPC?
Eligible costs of the Action
What are the obligations of a Partner when dealing with an HPC?5. Final Provisions
5.1. Derogations to the General Rules and Procedures
5.2. Interpretation
5.3. Contractual and regulatory sanctionsAnnexes
ANNEX 1 – PROCUREMENT GLOSSARY
ANNEX 2 - SAMPLE DECLARATION FOR CANDIDATES & TENDERERS
ANNEX 3 - DUE DILIGENCE AND RISK MANAGEMENT IN PROCUREMENT
The importance of good procurement planning
Table - Tips Before launching a procurement procedure
Risk management
Organisations' procurement profile and capability
Analysing the Procurement Portfolio and Developing a Procurement Profile
Analysing the Organisation's Procurement Function and Capability
Table – Measuring Results and Possible Indicators
ANNEX 4 - SAMPLE DECLARATION FOR MEMBERS OF EVALUATION COMMITTEES